New
HQ approved
A proposal to build Defence’s new joint operational headquarters
near Bungendore in NSW has been approved by the Parliamentary
Standing Committee on Public Works.
The works will cover the construction of facilities and infrastructure
and the installation of the command, control, communications and
information systems to provide a more responsive and flexible
operational command and control capability for the ADF.
Construction of the $300 million headquarters is scheduled to
start in the middle of next year. Preliminary engineering and
design studies have been undertaken.
It is expected the new headquarters will be fully operational
in 2007-08. A two-stage tender process for the headquarters has
begun, with companies asked in April to register interest in financing, constructing and maintaining the facility and providing
ancillary services.
When the facility is commissioned, Defence will lease the headquarters
for a term of 30 years, according to Defence Minister Robert Hill.