 |
|
A
heavy roller takes a break on the side of a new all-weather
track.

A sapper from 18 CE Sqn begins breaking up Airport Road.

|
|
Lt
Rob Lang shows OC 18 CE Sqn Maj Jason Hedges the new culvert
built into the Bamboo Creek Road.
Photos by Cpl Belinda Mepham, Army newspaper
|
Road
warriors
3CER
kick-start AACAP on Palm Island
By
Cpl Belinda Mepham
AACAP is underway on Palm Island, a Aboriginal community near Townsville.
In
the curtain-raiser to the project, 3CER began work more than a month
in advance to prepare initial works.
A tight
team headed by the 2IC 18 CE Sqn, project manager Capt John Daunt,
have nearly completed the task despite the typical tropical wet
affecting transport to the island.
After
the rain stopped we got started on the first part Bamboo Creek
Road, he said.
That
encompassed a 5km-long unsealed single-lane four-wheel-drive track
along with the construction of two culverts and the construction
of a rock gabion causeway.
The
Bamboo Creek Road allows the access from the township through the
hills to the repeater station that is the only telecommunication
point from the island.
The
second phase of 3CERs task was to repair Airport Road, the
main road, linking the airport to the main township of Palm Island.
We
replaced approximately 100 cubic metres of concrete, which had degraded
over the last 25 years.
An
important part 3CER had played during the deployment was to break
the ice with the local community before the main AACAP contingent
arrived.
OC
18 CE Sqn Maj Jason Hedges said logistics would have been a nightmare
because of the remote access to the island without a combined service
commitment.
It
would have been very difficult to even deploy on the task without
serious ties with LCM8s and RAAF air transport, he said.
Weve
had the RAAF elements working with us. Weve had three RAAF
plant operators working with us for almost the duration.
Theyve
provided specialist equipment and also its been a training
environment for them.
10FSB
supported us for the resupply runs using LCM8s and for vehicle delivery
between here and Townsville.
Weve
had equipment on loan from 17 Const Sqn and 21 Const Sqn.
A new
technique called concrete harvesting was practised during the repair
of Airport Road .
The
technique has been widely used by British and American engineers
during operations.
Project
deputy manager Lt Glen Billington said the opportunity to test and
assess the method would contribute to 3 Bde if they deployed on
operations.
Concrete
harvesting is basically a rapid airfield damage technique where
you cut out existing slabs of concrete to fit and repair craters
or damage from aerial delivered weapons and munitions, he
said.
A
slab is cut from the apron, or from a part of the airfield that
isnt heavily trafficked, then it is placed straight into the
pre-cut area that was damaged and youve instantly got a trafficable
surface, so its quite a fast and efficient way of repairing
an airfield.
Locally
employed civilians on the project have gained civilian qualification
for their participation.
|