06 May 2011
Stephen Smith MP
Minister for Defence
Strategic
Reform Program
The
Minister for Defence Stephen Smith and the Minister for Defence Materiel Jason
Clare today announced additional Strategic Reform Program (SRP) initiatives and
the first set of further accountability and procurement reforms for Defence.
The reforms will enhance Defence management and improve the delivery of
billions of dollars of investment in new capabilities being progressively
rolled out under the Force 2030 plan as set out in the 2009 Defence White
Paper.
In
line with the Strategic Reform Program, the Minister for Defence announced that
additional Defence efficiency measures would be achieved by a reduction in
Australian Public Service (APS) civilian staffing growth in Defence, and the
savings effected here would contribute to the Government’s return to a Budget
surplus and the Government’s broader fiscal strategy.
APS Savings: Civilian Employees
The
SRP will deliver over $20 billion in savings to reinvest in the delivery of
Force 2030. Early progress suggests that
more can be done. In addition to the SRP
measures already announced, the Government is announcing today a second phase
of SRP-related savings to be realised primarily through further improvements to
shared services design and implementation.
The
White Paper and the workforce and shared services stream of the SRP predicted a
net increase in the Defence APS workforce of 1,655 from 2010-11 to 2013-14.
Reforms
to shared services and other efficiency measures means that Defence can reduce
this overall forecast APS workforce growth by 1000 over the next three
years.
This
includes the application of the Government’s increased efficiency dividend to
Defence. Under this whole of Government
measure, the efficiency dividend will rise from 1.25 per cent to 1.5 per cent
in 2011-12 and 2012-13, before returning to 1.25 per cent for 2013-14 and
2014-15.
Reducing
the APS workforce growth will be achieved by natural attrition, not hiring new
staff and, if required, some limited voluntary redundancies.
Savings
from these reductions to forecast APS growth will be returned to the Budget.
There will be no
reductions to the Australian Defence Force military workforce as a result of
these changes.
Given priority accorded to maintaining support to operations, improving Navy
sustainment and enhancing capability development, the Joint Operations Command
(JOC), the Navy and the Capability Development Group (CDG) will be exempt from
these additional reductions to their forecast APS workforce.
Further Shared Services Reform
Defence
will undertake further externally-led reform and rationalisation of shared
services, both within Defence Groups, and across Defence as a whole. The intent is to realise workforce reductions
in corporate overhead functions in a way that does not reduce standards of
service in support of operations or capability development.
This
reform will be undertaken as part of the Strategic Reform Program, using its governance
and oversight processes, including oversight by the independent Defence
Strategic Reform Advisory Board chaired by Mr George Pappas.
All
Groups in Defence will be subject to this examination, with priority in those
areas where the largest gains in effectiveness and efficiency are likely to
occur. Planning will be completed by
late July, with implementation to commence in August 2011.
Project management accountability reforms
Mr Smith and Mr Clare
also released the first set of further accountability and procurement reforms.
In February Minister
Smith and Minister Clare foreshadowed they would bring forward a number of
reforms to improve accountability in Defence and project management.
This is the initial step
in that process.
It is essential that the
agreed recommendations of Kinnaird and Mortimer are fully implemented and built
upon.
In 2003 the Kinnaird
Report recommended a number of reforms which led to the two-pass approval
system, the creation of the Capability Development Group and the Defence
Materiel Organisation as a prescribed agency under the Financial Management and
Accountability Act.
Most of the Kinnaird
reforms have been implemented and have had a positive impact.
In 2008 the Mortimer
Review into Defence Procurement and Sustainment made 46 recommendations.
The Government agreed to
42 of them in full and three in part.
Many of these
recommendations have been implemented including increased investment in Defence
industry skills and incorporation of improved commercial practices into Defence
procurement.
Some of the key
recommendations have not yet been fully implemented.
Defence will now
accelerate the implementation of all outstanding agreed recommendations made by
Mortimer as a matter of priority.
This includes:
· project directives issued by the Secretary of
the Department of Defence and the Chief of the Defence Force to ensure
Defence acquisitions progress according to Government direction; and
· benchmarking all acquisition proposals against
off-the-shelf options where available.
In addition to this, the
Government is today announcing a small number of reforms that build on the
recommendations of Kinnaird and Mortimer.
These reforms will focus
on improving project management and minimising risk at project start and
identifying problems early.
They include:
· The introduction of a two-pass approval system for
minor capital projects valued between $8 million and $20 million;
· Implementation of an Early Indicators and Warning
system;
· The expansion of the Gate Review system; and
· The introduction of Quarterly Accountability
Reports.
Details of these reforms
are attached.
Over the coming months
the next stages of reform will include the Government’s response to the Black
Review into Accountability and Governance in the Defence Department and the
Government’s response to the Rizzo Review into the Maintenance of Naval Ships.
Project Management Accountability Reforms
Mortimer Reforms
As a matter of priority
Defence will accelerate the implementation of the agreed recommendations of the
Mortimer Review that have not yet been fully implemented.
These include:
- Cost-benefit analysis of projects that are not
off-the-shelf purchases
to rigorously review the project to assess the cost and risk against
off-the-shelf purchases.
- Establishing Project Directives to provide clear direction to Defence on
decisions made by the Government regarding Defence capabilities.
- Establishing an independent Project
Performance Office within
DMO to review projects and assist project teams to solve problems.
- Regular reporting to Government requiring Capability Managers to provide
advice on the status of capability development projects for which they are
accountable.
- Creating a more disciplined process for
changing the scope of a project
including the requirement that Defence seek the Government’s approval for
significant changes to the scope of a project.
The Government will also
request the Auditor General conduct a planned audit of the implementation of
the Mortimer Report in the second half of this year.
Two-Pass approval for minor capital projects
Defence will immediately
implement a two-pass approval system for minor capital equipment projects
valued between $8 million and $20 million.
Minor
capital projects are those valued at less than $20 million. Minor projects are not included in the
Defence Capability Plan. They cover new
equipment, modifications to existing equipment or enhancements to new
equipment. In 2010-11, the planned
budget for minor capital projects is around $150 million and there are
about 105 minor capital projects underway.
The two-pass approval
system recommended by Kinnaird has been successful in improving the budget,
schedule and capability delivery of major projects.
Major projects which
have been through the two-pass system demonstrate a 20 per cent to 25 per cent
improvement to their schedule when compared to those that did not.
This same rigour will
now be applied to minor capital projects.
These projects will now
involve a formal business case for two-stage approval by the Minister for
Defence.
Second pass approval for
minor capital projects will require Defence to provide the Minister with tender
quality data upon which to base decisions.
Early Indicators and Warning System
Defence assesses that 80
per cent of problems with Defence capability projects occur in the first 20 per
cent of the project’s life.
That is why it is important to pick up problems
early.
One of the biggest challenges in Defence
procurement is projects running late.
The earlier these issues are picked up, the earlier the problem can be
fixed.
The Government will implement an Early Indicators
and Warning System. This system will help identify and correct potential
problems with projects.
A set of triggers will
be established to give early warning of projects which are running late,
over-budget or not delivering the capability required.
The Government expects
that a substantial number of projects may activate the triggers. The purpose of
the system is to identify problems early so appropriate action can be
taken to remediate them.
The Minister for
Defence, the Minister for Defence Materiel, the Secretary of Defence and the
Chief of the Defence Force will be advised when these triggers are activated.
When a trigger is
activated Defence will conduct an internal review of the project and recommend
whether a full diagnostic examination (a Gate Review) is required and should be
conducted.
The initial triggers for
each project stage are set out below. These will be adjusted or added to as the
system matures.
Post-first
pass triggers:
Triggers will be activated if it is assessed that:
· the project is likely to go outside a parameter
agreed by Government at First Pass, as reflected in the respective Project
Directive by the CDF and Secretary;
· a significant milestone will not be achieved within
three months of the schedule approved by Government at First Pass; or
· the project cannot meet the essential requirements
within the cost, schedule and risk levels approved by Government at First Pass.
Post-second
pass triggers:
Triggers
will be activated if it is assessed that:
· the schedule for meeting Initial or Final
Operational capability will be delayed by 10 per cent or more for off-the-shelf
capability, 20 per cent or more for local adaptation of off-the-shelf
capability and 30 per cent or more for developmental projects.
· the project’s costs will exceed its approved
budget;
· the contractor is not meeting promised capability
or schedule milestones or exceeding approved costs;
· policy or legislative changes are likely to
increase the project’s schedule or cost;
· an essential capability requirement will not be
met;
· emerging requirements or regulatory or safety
standards are different to those at the time the project was approved by
Government and will materially affect the project;
· industry engaged in the project does not have the
required workforce or financial capacity or management commitment to meet critical project milestones; or
· project risks have increased beyond the parameters
agreed by Government.
The Defence Annual
Report will publish details of the action taken on projects as a result of an
early warning indicator being triggered.
Full Diagnostic Reviews
As foreshadowed in the
2009/10 Defence Annual Report and the 2009/10 Australian National Audit Office
Major Projects report, Defence will expand the use of the full diagnostic
review of projects, known as Gate Reviews.
Gate Reviews commenced
in 2009 for selected high value and highly complex projects and have proven
very effective in the early identification and resolution of problems.
All major projects
managed by the Defence Materiel Organisation will now undergo at least one Gate
Review per year.
Gate Reviews will also
be extended to other areas of Defence including Chief Information Officer Group
and Defence Support Group.
These reviews will
normally be linked to a key project decision point or milestone.
Reviews will also be
conducted in cases where the Government or Defence have concerns, or where a
project’s early indicator or warning is triggered.
A Project Manager will
also be able to request a Gate Review to enlist senior management assistance to
resolve significant issues.
A Gate Review Board will
be convened for each review.
A number of independent
experts will be contracted to provide advice to these reviews.
Quarterly Accountability Reports
There is a need for more
regular and rigorous reporting to Government on high priority projects.
Accordingly, there will
be a quarterly report to the Minister for Defence, the Minister for Defence
Materiel, the Secretary of the Department of Defence and the Chief of the
Defence Force on designated key projects.
The report on each such
project will be formally signed off by the Chief Financial Officer, the Chief
Executive Officer of the Defence Materiel Organisation, the Chief of the
Capability Development Group and the relevant capability manager, generally the
relevant Service Chief.
This will help improve
accountability and pick up problems early.
This will alert senior
Defence officials and Government to problems in projects so that an appropriate
remediation plan can be developed early and acted on.
Reports of this nature
are consistent with both the Kinnaird and Mortimer Reviews and will now be
implemented.
Such reporting will
begin at the next quarter, 1 July 2011, with the first such reports delivered
in October.