(1) to (5) For a list of Defence’s significant reviews, please refer to the table below.
| Review | Commenced | Concluded | Response | Cost |
|---|---|---|---|---|
| Medium Airlift Continuous Improvement Project | July 2009 | Initial review expected to be completed by end 2010 with potential for further initiatives implemented post 2010 | Response not applicable | $294,000 |
| Wide Area Surveillance Improvement Project | October 2009 | Initial review expected to be completed by end 2010 with potential for further initiatives implemented post 2010 | Response not applicable | Nil |
| ASIO T4 PSRR – COAG Mandated Review of “Vital” Australian Government Critical Infrastructure | September 2009 | March 2010 | Response not applicable | $38,720 |
| Strategic Review of Naval Engineering | July 2009 | November 2009 | Response not applicable | $144,189 |
| Review of the Reserve Service (Protection) Act | April 2007 | September 2009 | The Government is currently considering these recommendations | $78,610 |
| Review of the Army Reserve Approved Future Force | May 2009 | August 2009 | The Government is yet to consider the outcome of this review as it will be considered holistically as part of the Rebalancing Army Implementation Plan | Nil |
| Review into Australian industry’s capacity and capability to support Defence’s Electronic Warfare | December 2009 | April 2010 | Defence will consult with the Government on the results | $256,248 |
| Australian Strategic Policy Institute review into Defence’s capability planning | October 2009 | December 2009 | Defence will consult with the Government on the results | $161,000 |