| Senate Notice Paper Question No 1438 Schedule Number: 300155 |
Publication Date: 14 May 2009 Hansard: Pages 2995-7 |
|
Defence: Programs |
Senator: Johnston | |
Senator Johnston asked the Minister representing the Minister for Defence, upon notice, on 18 March 2009:
Senator Faulkner - The Minister for Defence has provided the following answer to the honourable senator's question:
| Project No | Project Name | Revised Initial Operational Capability (IOC) | Delay Comment | Project Value ($m) |
|---|---|---|---|---|
| AIR 5077 Phase 3 | Airborne Early Warning and Control System | December 2011 | Technical problems with radar and electronic support measures subsystems and integrated system performance. | 3999.262 |
| AIR 5276 Phase 8B | AP-3C Electronic Support Measure Upgrade Project | September 2012 | Protracted contract negotiations. | 127.226 |
| AIR 5402 | Air-To-Air Refuelling | Mid-late 2010 | Prime Contractor delays associated with the design, installation and testing of the new aerial refuelling and military avionics systems. | 1997.438 |
| JP 2077 Phase 2B.1 | Military Integrated Logistics Information System | October 2009 | Contractor delays due to poor quality processes and project management. | 128.004 |
| JP 2077 Phase 2B.2 | ADF Deployable Logistics System | 2012 | As a consequence of issues with Phase 2B.1 delivery, Defence has suspended negotiations with contractor until successful delivery of core Phase 2B.1 software. | 92.786 |
| JP 2085 Phase 1B | EO Reserve Stocks | 2009/10 (for Excalibur) | Deliveries of Excalibur Precision Guided Munitions have been delayed while awaiting the finalisation of tests and trials to allow full material release. Partial deliveries in 2008-09 will allow full certification and introduction into service to be completed by 2009-10. | 214.341 |
| JP 5408 Phase 2B | GPS Enhancement For ADF Platforms | LAND – November 2011 AIR – January 2012 SEA – October 2010 |
The IOC dates for all platforms have slipped due to delays in the US development program. | 62.711 |
| SEA 1401 Phase 3 | Survey Motor Launch Upgrade | 11 August 2009 | IOC (first upgraded Survey Motor Launch) deferred by 10 weeks due to two-week Commonwealth induced postponement (documentation review) and eight-week excusable delay arising out of unforeseen requirement for full crew safety audit / training period to be conducted. Defence examining options to minimise impact on overall schedule and Final Operational Capability. | 63.92 |
| JP 129 Phase 2 | Airborne Surveillance for Land Operations | New IOC under development | Cancellation of the acquisition and in-service support contracts with the contractor in 2008 has delayed the introduction of this capability. Defence has since conducted an initial analysis of alternative Tactical Unmanned Air Vehicle systems, and finalising its review of the essential criteria that will be utilised to shortlist candidate systems for detailed consideration. Following this analysis, a new IOC will be set. |
147.026 |