| Senate Notice Paper Question No 458 | Publication Date: 20 August 2002 Hansard: Pages 3408-9 |
|
Defence: Campbell Park Offices |
Senator: Evans | |
Senator Chris Evans asked the Minister for Defence, upon notice, on 15 July 2002:
With reference to an article published on 5 June 2002 in the Australian Financial Review which stated that $30 million was spent refurbishing Campbell Park offices before their sale:
Senator Hill - The answer to the honourable senator's question is as follows:
| Building Work | |
| Internal Demolition of 20 year old fitout | $ 0.675m |
| Upgrade on floor mechanical/electrical/ hydraulics/fire services | $ 5.860m |
| Upgrade security/entry doors | $ 0.653m |
| New ceilings/walls/carpets/painting | $ 2.517m |
| Project Consultant/Design costs | $ 0.403m |
| Construction Contractors Costs | $ 1.104m |
| Building Work Total | $11.212m |
| Fitout/Associated Costs | |
| New workstations/furniture/storage | $10.170m |
| Communications cabling | $ 3.972m |
| Relocation costs | $ 0.958m |
| Project Consultant/Design costs | $ 0.985m |
| Construction Contractors costs | $ 2.703m |
| Fitout Work Total | $18.788m |
| Project Total | $30.000m |