| Senate Notice Paper Question No 418 |
Publication Date: 20 August 2002
Hansard: Page 3378 |
Defence: Air Warfare Destroyer Project
|
Senator: Evans |
Senator Chris Evans asked the Minister for Defence, upon notice, on 10 July 2002:
With reference to the air warfare destroyer project, it has been indicated that the study phase for Sea
4000 will cost $30 to $50 million:
- Can a breakdown be provided of the costs for this study phase, given the size of the proposed
budget, including how much will be spent on consultancies and travel.
- What are the timelines for the study phase.
- Can a comparison be provided with the costs of similar study phases for other projects, for example,
the Anzac frigates, Collins class submarines, Air 87.
Senator Hill - The answer to the honourable senator's question is as follows:
- As this project phase is still under detailed consideration as part of the acquisition strategy, a cost
breakdown cannot be provided at this stage.
- The proposed timeline for the studies is still under consideration and not yet approved.
- The Collins Class Submarine Project conducted a similar Project Definition Study in the mid 1980s
that had an estimated cost of $33m (1985 value) or approximately $45m in 2002 dollars. An examination
of other projects has indicated no similar pre contract definition studies to that proposed
by Air Warfare Destroyer have been conducted. Projects examined include the Air 87, ANZAC
Frigates, and Patrol Boat projects.