4 -Takeover- CMS:
......• Commences operation, maintenance and support to the Facility.
......• PSC redirection of Defects to Construction Contractor.
......• CMS responsible for operation and maintenance of Stage or Works except those determined as a Defect.
|
4 - Takeover - Construction Contractor:
......• Manages Defects as required by Defect Liability requirements of the Contract.
......• Complete Post Activity Report requirements of the ECC (usually no later than 2 months after completion.
|
4 - Takeover - PMCA:
......• Monitors and confirms all Defence closed out and and rectified promptly, extend DLP periods as required.
|