SBC Step 9 - Obtain Sponsor Approval
Activity Considerations Outcome

1) Provide the SBC to proponent branch and project sponsor for endorsement as modified.

a) Under $4.5 million – seek endorsement and approval by DGIAD then sponsor.

b) $4.5 million and over – seek endorsement from DGIAD and sponsor and seek DISC consideration.
  • A fully completed SBC which contains all relevant collated information.

  • Approved and endorsed SBC.
  • Updated Plan by DIFP.
  • Stored on project file, G drive and DEMS.
2) Inform DIFP to update Infrastructure Development Plan.