Activity Considerations Outcome

1) Conduct final Stakeholder review of draft SBC and agreement to proceed.

Note: Stakeholders should have been consulted in the development activities. As a result, a second review may not be required at this stage – the relevant project staff may make this decision at this point depending on the scope of the SBC.

  • It is mandatory that at this stage environmental, heritage, risk and design acceptance authority reviews occur – allow two (2) weeks for this review to occur internally and for comments to be provided to the relevant Project staff
    (Refer to Document Review Process for further information)
  • It is mandatory for DLPSI to be involved
  • A draft SBC which outlines all relevant considerations to ensure that options submitted have been carefully considered.
  • To confirm stakeholders concurrence and where this does not occur identify any divergent issues.
  • Feedback collated and stored on project file