Budget Year (Year Zero) – Tender Approval and Raise PO
|
Outcome:
|
|
| Activity | Considerations |
|
1) Receipt of completed TEBR and supporting information from CMS. |
|
| 2) Review of the TEBR update by CMS (if needed) | |
| 3) Approval of the TEBR by DSG Delegated Officer | CPG require that Contract Approval Delegate (DSG Officer) is not the same as the person who approved the PFAS. CMS compliance with CPG's and the DPPM is the subject of CMS Compliance Indicator 3201. |
4) The DSG Program Manager requests purchase orders be raised in accord with the Tendered Sums by completing a Financial Approval and Purchase Order Submission Form. The completed form along with the Project file and approved PFAS listing the approval for the project is then forwarded to the FACOPS Finance Cell. |
The Purchase Order Submission is to be submitted with a copy of the Facilities Acquisition Strategy. In the field “Procurement Approver” insert the words ‘Refer Attached PFAS' and who approved it and the date of approval. |
| 5) Interim Defence Contract Register Contracts are to be documented on the Interim Defence Contract Register when the PO amount is >$90,909. The IDCR Form is an optional form that assists project staff with data entry into the IDCR in accordance with Senate Order 192. Exclusions are listed in the Defence Procurement Policy Manual at page 5.8.7. | Interim Defence Contract Register |
| 6) ROMAN Purchase Orders once issued must be added to the Project in DEMS through the liability field. The Purchase Order details will then display on the Purchase Order tab. Purchase Orders must be added to the Project Details in the Attached Works screen before the Work Requests can be assigned to the contractor's Work File |
Refer to the FACOPS ROMAN and DEMS Purchase Order Guideline. |
Note - FACOPS Procurement Approval of the TEBR represents Step 3 of the CPG's (Contract Recommendation Approval) and raising of the PO represents Step 4 of the CPG's (Purchase Order).
|
|