Budget Year (Year Zero) – Tender & Award Contacts
|
The CMS Project Manager is to conduct the tender process in accord with the approved PFAS and PTP. Note: that while these activities are part of the Project Delivery process in Budget Year (Year Zero), it is recommended that they be commenced as early as possible ie. in Year Minus One. Outcome:
|
|
| Activity | Considerations |
|
Specification 1) Detailed documentation in accord with the approved Project Scope, Design, Site Selection and Disposal Requirements. |
Refer to Section: Update the Pre-tender estimate. Pre tender estimates are subject of CMS Performance Indicator 3251. |
Standard CMS Sub Contracts 2) CMS to use the sub-contract as approved in the PFAS. These sub-contracts are standard for Planned Works under the CMS contract. |
Standard CMS sub-contracts are:
|
RFT Documentation 3) Request for Tender documentation is provided as part of the standard CMS sub-contract documents. |
Standard RFT documentation includes:
Tender process must comply with Commonwealth Procurement Guidelines (CPG). Compliance with the CPG’s and the DPPM and is the subject of CMS Compliance Indicator 3201. |
Determine if a Tender Evaluation Board. 4) A TEB is not normally required for simple procurements where the goods/services/works are under $80,000. A TEB is required if the procurement is categorised as Complex or Strategic and the goods/services/works are valued at more than $80,000. |
Must be undertaken in accordance with the approved PFAS and PTP |
Appointment of the Tender Evaluation Board. 5) TEB should comprise a minimum of 3 people selected on the basis of experience and knowledge of the subject matter. |
|
| 6) Each board member should familiarise themselves with the projects background and outcomes. | |
| 7) Prior to the opening of tenders the Chairperson should request a meeting of the board members to discuss any variance to the Weighting for each criterion. The exception being price which is normally weighted at 40%. | Variance in the Cost Weighting requires the submission of a business case in the form of a minute to the DSG Regional Manager. |
Opening Tenders. 8) Tenders are to be opened by three individuals who will not take part in the Tender Evaluation Board. After opening the group determines which submissions are conforming and which are not. Non-Conforming submissions are documented. |
See section 5.4 of Part A Tender Process and Tender Evaluation Policy for guidance on the opening and recording of tenders. See section 5.5 of Part A Tender Process and Tender Evaluation Policy for guidance on conforming / non-conforming tenders. |
Evaluation of Tenders. 9) Each member of the Evaluation Board is to be given a copy of each compliant tender. Once all of the board members have completed their individual evaluations the Chairperson arranges for the Board to meet to document their findings. The individual scores are transferred to the Tender Evaluation Board Report. The individuals scores are then combined to produce a board score which is then taken forward and evaluated against the tender price. The weighting for each criteria and the price then give the tender outcome in order of merit depending upon their capability to deliver a Value for Money outcome. |
Value for money is the principle criteria for evaluation of tenders. Additional criteria are:
|
TEBR 10) When the TEB review is complete and agreement reached a Tender Evaluation Board Report is to be forward to DSG Program Manager for approval to award contracts. |
Template TEBR |
Award Sub-contract 11) CMS to award the sub-contract in accord with the approved TEBR and Purchase Order. |
Invoicing from Sub-contractors must reflect the cost components in the Purchase Order |
Note- FACOPS Procurement
Award of the Contract represents step 5 of the CPG’s.