Budget Year (Year Zero) – Design
|
Project designs must not only mitigate the risk as documented in the CSIR but must also meet the objectives of the Program brief and stated needs of Defence users. Outcome: |
|
| Activity | Considerations |
|
1) Validate the User requirement. The Project Manager must confirm that the works requested in the CSIR are still required and that the users requirement is still the same. |
RMW Projects are undertaken to mitigate a specific set of risks as stated in the CSIR. Additional works requested by the customer post project approval should only be considered in those circumstances where they directly contribute to the projects outcome as approved by the DISC. |
| 2) Information is then taken from the scoping study to develop a functional design brief. | IAD Functional Design Brief Template
This document may be amended in line with the scale of works required. |
| 3)
Defence Green Building Requirements.
The Project Director will need to identify and include all Green Building requirements. |
Defence Green Building Requirements |
Source Design 4) The Design for the new structure may be developed in house where the capability exists or contracted to an Architect or other design agency. Design costs are to be taken out of the project budget. Should there be a requirement for specialist consultation eg. Geological or Hydraulic Surveys then these costs should be placed against Work Planning Fees. |
|
Review Design 5) Design reviews meetings are conducted by the CMS Project Manager at pre determined intervals. Present at the meeting should be:
Technical authorities and Base Services may also request involvement in the review activity. The Customer Units Commanding Officer signs as approving the design. |
The IAD Design Review Template may be used to support the design review process. This document may be amended in line with the scale of works required. Design is normally reviewed at:
|
Approval of Design 6) Once the design is complete, it is approved in writing by the:
Technical Authorities and Base Services may request to be involved in the approval of the design. |
Departures from the approved design are not permitted. This is the subject of CMS Compliance Indicator 3202. |