Budget Year (Year Zero) – 2nd Quarterly Review
|
|
The purpose of the Quarter 2 Regional Review is to:
Outcome: |
| Activity |
|
1) Two weeks prior to the review, EFPO will ask for the region to supply the up to date monthly Program Status Report to enable analysis for the Program AVA and Budget AVA updates discussed at the quarterly review meeting. |
| 2) Regions are to produce the reports in the Quarterly Review Information Pack. |
3) Regions are to complete the Quarter 2 Estate Maintenance Program Status Report, using the monthly updated Program Status Report and additional data from the system reports in the Information Pack prior to the arrival of the Estate Maintenance Review team (EFPO). This is to be completed prior to the arrival of the Estate Maintenance Review team (EFPO). |
4) Estate Maintenance Review team (EFPO) commences the Quarter 2 Review by initiating a series of interviews with nominated Region stakeholders including, but not limited to:
Primary areas of review in the Q2 Review are:
|
5) Estate Maintenance review team (EFPO) consolidates all information collected through the Quarter 2 Review and prepares draft Region Quarter 2 Review report, including the Quarter 2 AVA’s as part of the updated Estate Maintenance Program Status Report. The report is to include any remedial actions agreed on by the Region. |
| 6) EFPO approves draft Region Quarter 2 Review report for release. |
| 7) Quarter 2 Review report submitted through ASEP and DGR&B to Region by EFPO. |
| 8) Regions are to keep the Estate Maintenance Program Status Report up to date on a weekly/monthly basis. The subsequent quarterly reviews are a checkpoint to confirm the status of the program. |