Budget Year Minus 1 - Delivery Plan – Procurement (PFAS/PTP)

The Projects Delivery Plan is developed by the CMS in response to the Program Brief from DSG. The CMS Project Manager assesses the works and prepares in consultation with DSG a forward plan covering:

  • Procurement Plan (Projects Facility Acquisition Strategy and Projects Tender Plan)
    (this page).
  • Projects schedule (Gantt chart and milestones in DEMS);
  • Projects expenditure plans (phasings in DEMS); and

This is then used to determine the projects that can be delivered in the planned financial year and which will either be commenced but completed in an outer year or projects to be held over as pre-approved until the following year. Planned Works procurement is to be compliant with the CPG's and the DPPM and is the subject of CMS Compliance Indicator 3201.

Outcome:
Development of the Program Facilities Acquisition Strategy (PFAS ) and the Program Tender Plan (PTP) submitted to DSG for the Procurement Approval to commence procurement of Estate Maintenance Projects.
Activity Considerations

1) CMS Project Manager to prepare PFAS Part B and PTP Part B for Estate Maintenance approved works.

Aggregations of approved projects into “super projects” for purposes of delivery efficiency are to be shown on the PFAS Part B.

PFAS Part B Template

PFAS Overview Flowchart contains a useful guide to CPG compliant procurement using the PFAS process.
CMS is able to contract members of Defence Panels through the established arrangements of the panels themselves.

HNOD Minute: CMS use of Defence Panels
Guidance for CMS engagement of DIP and DUXOP panellists
Guidance for CMS engagement of DEHP panellists
Template Letters For Engaging DIP panellists
Template Letters For Engaging DUXOP panellists
Template Letters For Engaging DEHP panellists

2)  CMS to prepare PFAS Part B Template for approval in conjunction with PFAS Part B submission.  
Program Tender Plan
3) Based on the determinations documented in the PFAS Part B, the same list is prepared for the Program Tender Plan (PTP) Part B.

PTP Part B spreadsheet (PTP Part B Template) is to include information about the pool of membership for tender Evaluation Boards. Sample information is provided on the template.

Given the dimensions of both PFAS Part B and PTP Part B spreadsheets, printing in A3 is recommended.
4) The DEMS Project Milestones report, that identifies key planned milestone dates for the projects in the PTP reports is also to be provided.  
5) Approvals for the PTP Part B, mirror those for the PFAS Part B.  