Budget Year Minus 1 - Program Brief
|
The Program Brief documents the approved FACOPS Planned Works Program. It describes the broad scope of works, objectives to be delivered, logistical and other constraints on the project. The Program brief is prepared in consultation with the CMS. Outcome:
Structure of the Program Brief
|
|
| Activity | Considerations |
|
1) Update and issue the Regional Planning Brief on receipt of the approved FACOPS Program and Budget. |
Regional Planning Brief is prepared by Regional Estate Development Manager and covers the following issues:
|
| 2) Region to take the Q0 Program Status Report provided by DEO containing the list of approved projects as approved by the DISC and to add those current year project that are forecast to be OC into the following year. Program Status Report Explained |
DISC approval is provided in the form of the "Q0 Program Status Report". Current year OC projects are identified in the latest up to date version of the regions current year Program Status Report. |
3) Confirm the budget for planned works in accordance with program advice from DEO. Determine over-budgeting amount for target end of year achievement as a percentage of budget (eg 25%). |
Program advice from DEO, that includes the budget. |
| 4) DS Estate Program Manager to determine the target end of year % achievement for each project, to total the target end of year budget achievement. This is to be recorded on the "Program List" tab of the Program Status Report. | |
5) DS Regional Estate Development Manager and the DS Regional Estate Program Manager together are to develop the Program Brief for FACOPS Planned Works program, including information on all Project Packages in the approved program. Instructions for producing Program Brief information from the Q0 Program Status Report. |
The Program Brief contains:
|
6) DS Estate Development Officers (or technical equivalent such as SEM, REO) are to provide a Project Brief for all new projects in the program of planned works. The completed project brief document is to be attached to the project record in DEMS. Existence of the project brief on DEMS is also to be confirmed on the Program Brief via the table on the "Program List" tab on the Program Status Report. An example is provided on the Project Brief template. |
The project brief is to contain:
|
| 7) DS Estate Program Manager is to provide the completed Program Brief to CMS for planning the delivery of the program. This should be done by end March at the latest and preferably by end February. This is to be provided via the Contract Administrator in accordance with the CMS Contract. | The earlier this is completed, the earlier the CMS can commence delivery planning. |
| 8) CMS commences preparation of the Projects Delivery Plan. | The resultant Work Program is the subject of CMS Compliance Indicator 3207. |
| 9) Update to the program agreed throughout the year can be communicated to the CMS through a re-issue of an updated Program Brief. | |