| Tasks |
Step 1 Engage Probity Adviser (Projects >$6m, inc GST) (see ID Directive No 15) |
Step 2
If Approved in PDDP, Engage a Legal Service Provider. |
Step 3 Commence tender processes for PM/CA and other approved pre-planning contractors in accordance with PDDP. |
Step 4 Invitation to Register (if two-stage process has been approved) |
| |
Step 4a
Draft ITR documentation |
| |
Step 4b Access DIP, DEHP, DUXO panel arrangements, if appropriate |
| |
Step 4c Advertise on AusTender if Open tendering |
| |
Step 4d Registration of submissions |
| |
Step 4e Conduct Evaluation, in accordance with approved Evaluation Plan |
| |
Step 4f Produce Registration Evaluation Board Report (REBR) |
| |
Step 4g Executive Review and Approval (ERA) of REBR and Shortlist |
| |
Step 4h
Notification and Debrief |
Step 5 Request for Tender/Proposal (following ITR stage or for single stage process) |
| |
Step 5a Draft RFT/RFP/RFQ documentation |
| |
Step 5b Access DIP, DEHP, DUXO panel arrangements, if appropriate |
| |
Step 5c Advertise on AusTender if single stage and Open tendering |
| |
Step 5d Tender Registration |
| |
Step 5e Conduct Evaluation in accordance with approved Evaluation Plan |
| |
Step 5f Produce Tender Evaluation Board Report (TEBR) |
| |
Step 5g
For Projects >$6m, inc GST - Probity Adviser to review TEBR and deliver Probity Report |
Step 6
Produce Negotiation Plan, if required |
| |
Step 6a Executive Review and Approval (ERA) of TEBR and Negotiation Plan |
|
Step 7
Conduct negotiations in accordance with Negotiation Plan
|
Step 8 Produce Contract Approval financial submission (incorporating Negotiated Outcomes and Recommendations) |
| |
Step 8a
Submit to Delegate for financial approval |
Step 9
Raise PO in DEMSID (IAD Guide) |
Step 10
Exercise Contract Signatory delegation to execute Contract |