Tasks

Step 1
Validate User Requirements
Step 2
Develop Functional Design Brief FDB (Functional and/or Performance Based)
Step 3
Commence Design
Step 4
Review Design
  Step 4a (Review Design)
Complete Master Plan Feasibility Report
  Step 4b (Review Design)
Complete Concept Design Report
  Step 4c (Review Design)
Complete Schematic Design Report
  Step 4d (Review Design)
Detailed Design Report
  Step 4e (Review Design)
Finalise Scope of Works
Step 5
Obtain Design Certification
Step 6
Completion in accordance with the Contract