Design Progression Step 5 - Obtain Design Certification
Activity Considerations Outcome

1) IAD Project Officer to receive letter of certification from Project Manager and/or Designer, that design has been independently certified against Statutory and Defence requirements


Statutory Requirements satisfied:
  • Design certification
2) IAD Project Officer to receive a letter of approval from Project Manager and/or Designer that special conditions of contract have been addressed

Defence Requirements satisfied

3) IAD Project Officer maintains copy of letter of certification and approvals on project file  