Infrastructure Management (IM) |
| Site Navigation :: Home>Design Management/Progression>Obtain Design Certification |
Design Progression Step 5 - Obtain Design Certification |
||
| Activity | Considerations | Outcome |
1) IAD Project Officer to receive letter of certification from Project Manager and/or Designer, that design has been independently certified against Statutory and Defence requirements
|
Statutory Requirements satisfied:
|
|
| 2) IAD Project Officer to receive a letter of approval from Project Manager and/or Designer that special conditions of contract have been addressed |
Defence Requirements satisfied
|
|
| 3) IAD Project Officer maintains copy of letter of certification and approvals on project file | ||
Related Reference Material
- Design Services Contract Clause 2.10 and 2.11 & Manual
- Head Contract Clauses 8.3 and 8.4 & Manual
- Managing Contractor 8.18 and 8.19 & Manual
- Relevant compliance documentation received from Project Manager and/or Designer
- IM - Engineering and Maintenance section