Design Progression Step 5 - Obtain Design Certification
Activity Considerations Outcome

1) IAD Project Officer to receive letter of certification from Project Manager and/or Designer, that design has been independently certified against Statutory and Defence requirements


Statutory Requirements satisfied:

  • BCA
  • Disability access
  • OHS
  • Contractual requirements satisfied:
    • Refer Design Services Manual under Clause 4.1 (2.10(b), 2.10(d))
    • Refer Head Contract Manual under Clause 3.1 (8.3(c), 8.4(d))
    • Refer Managing Contractor Manual under Clause 3.1 (8.18(c), 8.19)
  • Design certification
2) IAD Project Officer to receive a letter of approval from Project Manager and/or Designer that special conditions of contract have been addressed

Defence Requirements satisfied

3) IAD Project Officer maintains copy of letter of certification and approvals on project file  

 