Design Progression Step 4e (Review Design) - Finalise Scope of Works |
||
| Activity | Considerations | Outcome |
| 1) Project Officer tasks Project Manager to finalise scope of works (100% design) required for Tender to be submitted to Industry to select a construction contractor. |
|
|
| 2) IAD Project Officer receives Final Design Review report from Project Manager | ||
| 3) IAD Project Officer to review to ensure required changes have been made based upon feedback received from stakeholders at the Detailed Design Report |
|
|
| 4) IAD Project Officer reviews Final Design Review Report |
|
|
| 5) IAD Project Officer provides Final Design Review Report to Project Director | ||
| 6) Project Director reviews Final Design Review report | ||
| 7) Project Director is satisfied all design issues have been adequately addressed |
|
|
| 8) IAD Project Officer provides feedback on Final Design Review Report to Project Manager | ||
| 9) Project Manager considers feedback and makes required amendments and/or provides justification for not making requested amendments to design. | ||
Stakeholders
- Sponsor
- User
- DEEP
- EPE
- Directorate of Training Area Regulation and Policy (DTARP) (for Ranges and Training Areas)
- DSO Regional Staff (Regional Manager, Planning Liaison Officer, Utilities/Energy Staff)
- DSO Regional CMS & GSS (Engaged via DSO Regional Staff)
- Document reviewers as identified at Concept, Schematic and Detailed Design Review phases (if necessary)
Related Reference Material
- ESD - Green Building Requirements
- ESD Section of Design Report Template - Refer to ESD - Green Building Requirements
- Engineering and Maintenance section