Infrastructure Management (IM) |
| Site Navigation :: Home>Design Management/Progression>Review Design>Finalise Scope of Works |
Design Progression Step 4e (Review Design) - Finalise Scope of Works |
||
| Activity | Considerations | Outcome |
1) IAD Project Officer tasks Project Manager to finalise scope of works (100% design) required for Tender to be submitted to Industry to select a construction contractor
|
|
|
2) IAD Project Officer receives Final Design Review report from Project Manager |
||
3) IAD Project Officer to review to ensure required changes have been made based upon feedback received from stakeholders at the Detailed Design Report
|
|
|
4) IAD Project Officer reviews Final Design Review Report
|
|
|
5) IAD Project Officer provides Final Design Review Report to Project Director |
||
6) Project Director reviews Final Design Review report |
||
7) Project Director is satisfied all design issues have been adequately addressed
|
|
|
8) IAD Project Officer provides feedback on Final Design Review Report to Project Manager |
||
| 9) Project Manager considers feedback and makes required amendments and/or provides justification for not making requested amendments to design. | ||
Stakeholders
- Sponsor
- User
- DEEP
- EPE
- Directorate of Training Area Regulation and Policy (DTARP) (for Ranges and Training Areas)
- DSO Regional Staff (Regional Manager, Planning Liaison Officer, Utilities/Energy Staff)
- DSO Regional CMS & GSS (Engaged via DSO Regional Staff)
- Document reviewers as identified at Concept, Schematic and Detailed Design Review phases (if necessary)
Related Reference Material
- Defence Green Building Requirements - Refer to Section 5.4 Delivery - Completion of Design
- ESD Section of Design Report Template - Refer to Green Building Toolbox
- IM - Engineering and Maintenance section