Infrastructure Management (IM) |
| Site Navigation :: Home>Design Management/Progression>Review Design>Complete Schematic Design Report |
Design Progression Step 4c (Review Design) - Complete Schematic Design Report |
||
| Activity | Considerations | Outcome |
1) IAD Project Officer monitors the development of Schematic Design Report |
|
|
2)) IAD Project Officer receives Schematic Design Report from Project Manager |
||
3) IAD Project Officer to review to ensure required changes have been made based upon feedback received from stakeholders at the Concept Design Brief |
|
|
4) IAD Project Officer provides Schematic Report to User, Sponsor and DEEP (these are mandatory referrals) and other key stakeholders |
|
|
5) IAD Project Officer to obtain from DSO Regional Staff an estimate of operating cost |
|
|
6) IAD Project Officer receives feedback on Schematic Report within the prescribed number of calendar days as contractually agreed to |
|
|
7) IAD Project Officer collates feedback |
||
8) IAD Project Officer provides Schematic Design Report to Project Director |
||
| 9) IAD Project Director reviews Schematic Design report. |
|
|
| 10) IAD Project Director is satisfied all stakeholders issues have been adequately addressed |
|
|
| 11) IAD Project Officer provides feedback on Schematic Design Report to Project Manager and/or Designer |
|
|
Stakeholders
- Sponsor
- User
- DEEP
- EPE
- Directorate of Training Area Regulation and Policy (DTARP) (for Ranges and Training Areas)
- DSO Regional Staff (Regional Manager, Planning Liaison Officer)
- DSO Regional CMC & GSS (Engaged via CSI NOD Regional Staff)
- Document reviewers as identified at Concept Design Review stage (if necessary)
Related Reference Material
- Schematic Design Review Report
- Design Services Contract Clauses – 2.2; 3.5; 4.1 6.2; 6.3 and 6.4 and 6.5
- Design Services Manual
- Head Contract Clauses - 3.1; 3.9; 6.2; 6.3; 6.4; 6.5; 6.6.
- Managing Contractor Contract Clauses - 3.1; 3.9; 6.8; 6.9; 6.10; 6.11
- Manuals for DSC, HC & MC
- Defence Green Building Requirements - Refer to Bookmark 5.3 Detailed Business Case (DBC)
- ESD Section of Design Report Template - Refer to Green Building Toolbox
- IM - Engineering and Maintenance section
- EPE Project Review & Assessment (PRAP)