Design
Progression Step 4b (Review Design) -
Complete Concept Design Report |
||
| Activity | Considerations | Outcome |
|
1) IAD Project Officer monitors development of Concept Design Report by Project Manager/Designer
|
|
|
|
2) IAD Project Officer receives Concept Design Report from Project Manager and/or Designer for review and consideration
|
|
|
|
3) IAD Project Officer facilitates stakeholder review of Concept Design Report. Stakeholders must include DEEP, EPE and Sponsor
|
|
|
|
4) IAD Project Officer to obtain from DSO Regional Staff an estimate of operating cost |
|
|
|
5) IAD Project Officer receives stakeholder feedback within number of calendar days as agreed. Project Officer has authority to authorise Project Manager and /or Designer to proceed if no feedback received within number of days agreed to within contract
|
IM Technical Regulatory Compliance Framework including:
|
|
|
6) IAD Project Officer collates feedback |
||
|
7) IAD Project Officer forwards Concept Design Report with stakeholder feedback to Project Director |
||
|
8) Project Director considers feedback, reviews Concept Design Report and provides guidance to IAD Project Officer |
|
|
| 9) IAD Project Officer collates feedback for Project Manager | ||
| 10) Feedback is addressed by Project Manager |
|
|
Stakeholders
- DEEP
- EPE
- User
- Sponsor
- DSO Regional Staff (Regional Manager, Planning Liaison Officer)
- DSO Regional CMS & GSS (Engaged via DSO Regional Staff)
Related Reference Material
- Design Review Repor Template
- Design Services Contract Clauses – 2.2; 3.5; 4.1; 6.2; 6.3 and 6.4 and 6.5
- Head Contract Clauses - 3.1; 3.9; 6.2; 6.3; 6.4; 6.5; 6.6.
- Managing Contractor Contract Clauses - 3.1; 3.9; 6.8; 6.9; 6.10; 6.11
- Manuals for DSC, HC & MC
- IM - Engineering and Maintenance section
- DSG Business Rule 11
- Green Building Toolbox - Refer to:
- Checklist for DBC (Minor project)
- Checklist for DBC (Major project)
- Budget Costing Tool for DBC
- WOL (Whole of Life) Costing for ESD Initiatives in DBC
- ESD Section of Design Report Template
- EPE Project Review & Assessment (PRAP)