Design
Progression Step 4a (Review Design)-
Complete Master Plan Feasibility Report |
||
| Activity | Considerations | Outcome |
|
1) IAD Project Officer determines if it is a Simple or Complex project by using the Site Selection checklist, and manages the Site Selection process. |
|
|
|
2) Site selection process considers identified locations for the facility.
|
|
|
|
3) Site Selection process gains endorsement for a location for the facility |
||
|
4) Delegate approves site selection |
||
| 5) Site is selected | ||
Stakeholders
- EPE
- DEEP
- Regional environmental staff (as participant on site selection board)
- Users
- Sponsors
- Land Planning
- DSO Regional Staff (Regional Manager, Planning Liaison Officer)
- DSO Regional CMS & GSS (Engaged via DSO Regional Staff)