HC Strategy - Head Contractor for Delivery Phase
Technical Authority: DGIAD
Subject Matter Expert: ADCC
Responsibility: DGIAD
   

 

HC Strategy Head Contractor for Delivery Phase

Tasks
Step 1
PM/CA to develop tender documentation for engagement of Head Contractor (HC-1 2003)
Step 2
Invitation to Register Interest (ITR)
(if a two-stage process has been approved)
 

- in appropriate circumstances the ITR stage may occur prior to obtaining Parliamentary Clearance -

 

Step 2a
Advertise on AusTender if approach is to open market

 

Step 2b
Registration of submissions

 

Step 2c
Evaluate in accordance with approved Evaluation Plan

 

Step 2d
Produce Registration Evaluation Board Report

 

Step 2e
Executive Review and Approval of REBR and shortlisted Registrants

Step 3
Request for Tender / Proposal (RFT/RFP)
(following ITR stage or for single stage process)
 

Step 3a
Advertise on AusTender (if single stage and open approach)

 

Step 3b
Receive Deeds of Confidentiality from Tenderers

 

Step 3c
Release RFT documents

 

Step 3d
Registration of Tenders

 

Step 3e
Conduct evaluation in accordance with approved Evaluation Plan

 

Step 3f
Produce Tender Evaluation Board Report (TEBR)

 

Step 3g
Probity Adviser to review TEBR and attach Probity Report

 

Step 3h
Produce Negotiation Plan (if required) and Preferred Tenderer Correspondence

Step 4
Executive Review and Approval of TEBR, Negotiation plan and Preferred Tenderer Correspondence
Step 5
Conduct contract negotiations (if required) with Preferred Tenderer in accordance with approved Negotiation Plan
Step 6
If > $15m (ex GST) notify the Minister for Defence of Contract of Award in accordance with ID Directive 18. Produce Contract Approval Financial submission in accordance with TEBR and contract negotiation outcomes
Step 7
Raise PO in DEMID
Step 8
DFS load funds against PO in ROMAN
Step 9
Exercise Contract Signatory Delegation to execute Head Contract