HC Strategy - DBC and Project Approvals Step 7 - PD to finalise DBC
Activity Considerations Outcome

1) Prepare Detailed Business Case (DBC).

  • DBC Template
    - PWC template
    - MINSUB/CABSUB template
  • Documents
    - Siting Boards
    - Environmental Clearances
  • Required project approval process
  • Draft DBC and other documents ready for approval.
2) Prepare DISC Agendum Paper for projects >$4.5M (exGST)

Please note:
a) refer to the DISC site within the IM which will provide policy on:

  • The process to be followed; and
  • The DISC Agendum Template.
b) Agendum Paper is to be provided 5 working days prior to each DISC meeting – DBC Project time line should reflect this.
3) Prepare draft PWC statement of evidence and referral if required.
4) Prepare draft MINSUB/CABSUB if required.