Construction Management to Project Finalisation Step 2 - Mobilisation and Site Establishment
Activity Considerations Outcome

1) All Defence personnel required to access the site to go through appropriate site induction conducted by the contractor representative

  • Site Induction
  • Contractor is ready to commence works

2) Defence Project Team receive dilapidation survey from Contractor

  • Joint inspection between Project Consultant and Contractor

3) Defence Project Team/Regional Office review and agree with dilapidation survey

.

4) Defence representative takes possession of the Defence site office

  • Refer to contract to determine whether contractor is to provide site office for Project Consultant and/or Defence.
5) Defence Project Team monitor contractor implementation of Environmental Management Plan
  • Ongoing validation
  • Liaison with Regional Environmental Officer
 

 