Construction
Management to Project Finalisation Step 1 -
Complete Conditions Precedent for Access to Site |
||
| Activity | Considerations | Outcome |
|
1) Defence Project Team finalises preparations for transfer of the site |
Specific issues relating
to:
Partial occupation
|
|
|
2) Defence Project Team confirms the environmental management plan and construction management plan are compliant with the ECC |
|
|
|
3) Project Consultant issues site access letter to construction contractor |
|
|
|
4) Defence Project Team arranges for general notice to base personnel that contractor has site access and is shortly commencing work |
|
|
Stakeholders
- CSI Regional Manager
- CSI Regional Environment Officer
- CSI Base Services Manager
- CSI Regional Planning Liaison Officer
- Base Commander
Related Reference Material
- Environmental Management Plan
- Construction Management Plan
- Defence Green Building Requirements - Refer to Section 5 Main Roadmap, Section 5.4 Delivery - Delivery Roadmap: 2nd Stage Approval to Final Completion, and Appendix B: Completion of ESD Design Process
- Green Building Toolbox - Refer to ESD Section of Building Users' Guide Template
|
|
|