Construction Management to Project Finalisation Step 1 - Complete Conditions Precedent for Access to Site
Activity Considerations Outcome

1) Defence Project Team finalises preparations for transfer of the site

  • Preparations to be considered in CSIR/SBC/DBC stage
  • Necessary Security clearances - as required
  • Security corridor for access to the site (Traffic access plan)
  • Base Induction for project staff (base hazards/OHS) (where appropriate)
  • Develop appropriate management plans (traffic, environment)
  • Preparation of method of works plan with base operations\sponsor (where appropriate)

Specific issues relating to:
All sites:

  • Delinated boundaries
  • Access to the services (metering)

Partial occupation

  • OH&S
  • Noise
  • Security
  • Trespass
  • Contractor is able to mobilise to the site and commence works

2) Defence Project Team confirms the environmental management plan and construction management plan are compliant with the ECC

  • Ensure that the ECC has been granted

3) Project Consultant issues site access letter to construction contractor

  • Nominate contractor as principal contractor for OHS

4) Defence Project Team arranges for general notice to base personnel that contractor has site access and is shortly commencing work

  • Advise Base Services Manager, Regional Planning Liaison Officer, Base Commander
 

 