Overview of Commissioning, Handover and Takeover Process |
||
|
The Commissioning, Handover and Takeover process commences in the initial stages of an infrastructure project. This provides an overview of steps to be taken in the Commissioning, Handover and Takeover process at the different stages of an infrastructure project. The roles and responsibilities are addressed in the relevant contract terms and conditions and shall need to be included in your projects tender documentation prior to release. This
Flowchart
shows the Commissioning, Handover and Takeover process diagrammatically.
The levels of the flowchart represent:
|
||
| Commissioning | Handover | Takeover |
|
Definition:
Commissioning takes place during the construction of the Works, before Completion (as defined in the relevant construction contract) of the Works. As indicated in the flowchart, Commissioning planning commences in design development. As part of the Commissioning process the DSC are responsible for specifying detailed commissioning requirements and acceptance criteria for achieving design intent, and for transferring the information to the Construction Contractor for the development of the Commissioning and Handover plan. The Construction Contractor is responsible for developing a Commissioning and Handover Plan, also to ensure that all Commissioning and Handover requirements are addressed and relevant stakeholders consulted as part of the process. The Commissioning and Handover requirements are detailed in the conditions of contract, reference clause 9.13 Commissioning and Handover. The IAD Project Officer / Director and the PM/CA are responsible for reviewing the Commissioning and Handover Plan prepared by the Construction Contractor. For all participants consultation with the relevant stakeholders is essential to ensure that all Commissioning and Handover requirements are addressed. Commissioning
is.... Another example of Commissioning is the installation of new aircraft into a newly-constructed hangar. Commissioning
is not.... |
Definition:
Handover takes place prior to, and at the time of Completion (as defined in the construction contract) of the Works. The Head Contract conditions of contract reference clause 13.1, Contractor to Notify, and in Head Contract Manual 5 Proforma Notices define completion requirements for the Head Contractor regarding Handover. The contractor shall provide appropriate certification and reports as part of Handover process. There may be minor defects or omissions in the Works but these do not prevent the Works from being reasonably capable of being used for the intended purpose, and can be corrected without prejudicing the convenient use of the Works. Importantly, the risk in the Works passes back to IAD (subject to the provisions of the construction contract eg. Defects Liability Period). The Construction Contractor is responsible for developing a Commissioning and Handover Plan, and to ensure that all Commissioning and Handover requirements are addressed. The Commissioning and Handover requirements are detailed in the Construction Contract. IAD and the PM/CA are responsible for reviewing the Commissioning and Handover Plan prepared by the Contractor and working with the stakeholders and the Construction Contractor to ensure that all Commissioning and Handover requirements are addressed. Handover
is.... Handover
is not.... |
Definition:
IAD passes responsibility for maintenance and operation of the Works to NOD; and IAD provides access to the Works to the user/sponsor. Takeover takes place after Commissioning and Handover. IAD and NOD are jointly responsible for developing a Takeover Plan to ensure that all Takeover roles, responsibilities and requirements are addressed. The Takeover Plan should be developed at the same time as the development of the Commissioning and Handover Plan prepared by the Construction Contractor and reviewed by IAD and relevant stakeholders. IAD is responsible for ensuring that all relevant matters in the Takeover Plan are also addressed in the Commissioning and Handover Plan prepared by the Construction Contractor. Takeover is a stage which is internal to Defence and therefore does not involve the Construction Contractor. Takeover
is.... Takeover
is not.... |