Infrastructure Management (IM) |
| Site Navigation :: Home>Commissioning, Handover and Takeover>Manage the Defects Liability Period |
|
Commissioning,
Handover and Takeover Step 9 - Manage
the Defects Liability Period |
||
|
Commence this step by Identifying the stakeholders (shown below) relevant to Defects Liability Period. |
||
| Activity | Considerations | Outcome |
|
1) Identify all Defects Liability Period requirements in the relevant contracts (construction contracts, CMS Contract, GSS Contracts) and the Commissioning and Handover Plan. |
The Defects Liability Period commences on Completion (and not when Takeover, being an internal Defence process only, is completed). Accordingly, this stage operates concurrently with Step 8 (Takeover). The Defects Liability Period usually extends for up to 12 months after Completion, but may be subject to extension in accordance with the provisions of the construction contract. The main purpose of the Defects Liability Period is to rectify Defects (as defined in the construction contract) in the Works. The construction contract contains detailed procedures in respect of the timing, responsibility and costs of rectifying such defects. The construction contract and the Commissioning and Handover Plan will also identify the extent of any planned and unplanned maintenance, and building tuning to be conducted by the construction contractor during the Defects Liability Period. This is intended to assist IAD / Project Director and NOD to distinguish between the respective responsibilities of the construction contractor and the CMS/GSS Contractors. Accordingly, the Defects Liability Period will be primarily managed by the IAD project team / Project Director having regard to the provisions of the:
with co-operation and assistance from NOD (Regional Office and Manager Technical Services).
|
As set out in the Commissioning and Handover Plan and the relevant contracts. Defects Liability Report. |
|
2) Ensure the construction contractor completes its Defects Liability Period obligations in accordance with the Contract and the Commissioning and Handover Plan. |
||
| 3) If not covered by the construction contract, take appropriate action (eg. through NOD to CMS Contractor, GSS Contractors) - eg. contact Help Desk and authorise expenditure. | ||
| 4) Co-ordinate design consultants, NOD (Regional Office and Manager Technical Services) and users/sponsors in respect of Defect Liability Period tasks (as appropriate). | ||
| 5) Conduct inspections and document inspection results and ensure that alternatives provided for in construction contract are appropriately implemented (eg. costs of rectification of defects etc). | ||
|
6) At the end of the Defects Liability Period, prepare Defects Report which documents Defects Liability Period activities, including inspection results and other actions taken in respect of defects, generally. This report will be due 14 days after the end of DLP to allow response time using the template provided by PD. |
||
| 7) Distribute copies of the Defects Report (as appropriate) and place original on project file. |
At the end of the defects liability period post occupancy evaluation should be undertaken by IAD in accordance with the commissioning / handover / takeover process on the IM. Key considerations of the POE include:
|
|
Stakeholders
- IAD Project Team / Project Director
- NOD (Regional Office and Manager Technical Services)
- User/Sponsor
- Construction Contractor
- Design Consultants
- CMC / CMS Contractor / GSS Contractor
- Technical authorities
- EEP for relevant projects
Related Reference Material
- Contract with the Construction Contractor
- Contract with the CMC / CMS Contractor
- Contract with the GSS Contractors
- Commissioning and Handover Plan
- Commissioning and Handover Report