Commissioning, Handover and Takeover Step 8 - Takeover |
||
Commence this step by
Identifying the stakeholders (shown below) relevant to Takeover. |
||
| Activity | Considerations | Outcome |
|
1) Review the Takeover Plan and update it as necessary. |
Takeover is the stage where:
Takeover takes place after Commissioning and Handover. IAD / Project Director and NOD are jointly responsible for developing a Takeover Plan to ensure that all Takeover roles, responsibilities and requirements are addressed. The Takeover Plan developed by IAD / Project Director and NOD will govern the respective roles and responsibilities during Takeover. Takeover is a stage which is internal to Defence and therefore does not involve the construction contractor. This stage operates concurrently with Step 9 Managing the Defects Liability Period). The Takeover plan must specifically identify ongoing requirements for environmental management as set out in the OEMP. |
As set out in the Takeover Plan. Takeover Report developed. |
|
2) Seek agreement and sign-off on any amendments to the Takeover Plan from IAD project team / Project Director, NOD (Regional Office and Manager Technical Services) and users/sponsors. |
||
| 3) Distribute copies of the revised Takeover Plan (if any) (as appropriate) and place original on project file. | ||
| 4) Complete asset roll-out tasks (see separate documentation on Financial Management). | ||
| 5) Implement procedures in Takeover Plan eg meetings, reports, information exchange. | ||
| 6) Prepare Takeover Report which documents Takeover activities prior to project completion and Handover. | ||
| 7) Distribute copies of the Takeover Report (as appropriate) and place original on project file . | ||
Stakeholders
- IAD Project Team / Project Director
- NOD (Regional Office and Manager Technical Services)
- User/Sponsor
- CMC / CMS Contractor / GSS Contractor
- Technical authorities
Related Reference Material
- Approved DBC
- Roles Plan
- Design Principles
- Contract with the Construction Contractor
- Contract with the CMC / CMS Contractor
- Contract with the GSS Contractors
- Takeover Plan
- Commissioning and Handover Report