Infrastructure Management (IM) |
| Site Navigation :: Home>Commissioning, Handover and Takeover>Handover |
Commissioning, Handover and Takeover Step 7 - Handover |
||
Commence this step by Identifying the stakeholders (shown below) relevant to Handover. |
||
| Activity | Considerations | Outcome |
|
1) Identify all Completion and Handover requirements in the relevant contract. |
Handover takes place after Commissioning and after Completion (as defined in the relevant construction contract) of the Works. The construction contractor is responsible for developing a Commissioning and Handover Plan to ensure that all Commissioning and Handover requirements are addressed. The Handover requirements will include the provision of certain documents and information (including as-constructed drawings, warranties, operation and maintenance manuals and approvals, building users' guide, utility management plan, training) required for the use, operation and maintenance of the Works. All Commissioning and Handover requirements to be addressed in the Commissioning and Handover Plan are to be set out in the construction contract, for example:
IAD / Project Director is responsible for reviewing the Commissioning and Handover Plan prepared by the Contractor and working with the stakeholders and the construction contractor to ensure that all Commissioning and Handover requirements are addressed. In Completion, there should only be minor defects or omissions in the Works which do not prevent the Works from being reasonably capable of being used for the intended purpose of the Works and which can be corrected without prejudicing the convenient use of the Works. |
As set out in the Commissioning and Handover Plan and the relevant contract. Commissioning and Handover Report (incorporating the Building User Guide and the Utility Management Report) |
|
2) Ensure the construction contractor has completed the Completion and Handover requirements in accordance with the Contract and the Commissioning and Handover Plan. Including compliance with any environmental remedial actions and incident reporting requirements. |
||
| 3) Co-ordinate design consultants, NOD (Regional Office and Manager Technical Services) and users/sponsors in respect of Completion and Handover tasks (as appropriate). | ||
| 4) Conduct inspections and document inspection results (including defects and EMS/ECC) and ensure that options provided for in construction contract are appropriately implemented eg rectification of defects, no issue of Notice of Completion, variations. | ||
|
5) Arrange issue of Notice of Completion (or equivalent) if Completion achieved. Ensure Post Activity Reporting requirements of ECC are complied with and finalise Post Activity Report. If activity includes disturbance/removal/remediation of contaminants or hazardous materials include contamination close-out reports. |
||
| 6) Finalise Commissioning and Handover Report which documents commissioning activities (see Step 6 Commissioning), inspection results and other actions taken in respect of defects, generally and which also includes the Building User Guide and Utility Management Plan. | ||
| 7) Distribute copies of the Commissioning and Handover Report (as appropriate) and place original on project file. | ||
Stakeholders
- IAD Project Team / Project Director
- NOD (Regional Office and Manager Technical Services)
- User/Sponsor
- Construction Contractor
- Design Consultant
- CMC / CMS Contractor / GSS Contractor
- Technical authorities
- EP&E (DEIM /DEPI)
- REO
- EEP
Related Reference Material
- Commissioning and Handover Plan
- Contract with the Construction Contractor
- ECC, EMS, EMP reports and any contamination investigations