Infrastructure Management (IM) |
| Site Navigation :: Home>Commissioning, Handover and Takeover>Develop the Takeover Plan |
Commissioning, Handover and Takeover Step 5 - Develop the Takeover Plan |
||
Commence this step by Identifying the stakeholders
(shown below) relevant to the preparation of the Takeover Plan to be
produced by IAD / Project Director and NOD. |
||
| Activity | Considerations | Outcome |
|
1) Obtain a copy of the Takeover Plan Template. |
The purpose of the Takeover Plan is to facilitate the smooth transition of the Works from IAD / Project Director to NOD and IAD / Project Director to the user/sponsor. IAD / Project Director and NOD are jointly responsible for developing the Takeover Plan to ensure that all Takeover roles and responsibilities are addressed. The Takeover Plan should be developed at the same time as the development of the Commissioning and Handover Plan prepared by the construction contractor. IAD / Project Director is responsible for ensuring that all relevant matters in the Takeover Plan are also addressed in the Commissioning and Handover Plan prepared by the construction contractor. Matters to be addressed in a Takeover Plan might include:
|
Takeover Plan developed. |
|
2) Document the matters to be addressed in the Takeover Plan Template. |
||
| 3) Seek agreement and sign-off on the Takeover Plan from IAD project team / Project Director, NOD (Regional Office and Manager Technical Services) and user/sponsor. | ||
| 4) Ensure that any key requirements of the Takeover Plan were incorporated into the tender and contract documentation for the engagement of the design consultants and the construction contractor (as appropriate). If not, address in accordance with the construction contract or design consultant contract (eg variation procedures). | ||
| 5) Distribute copies of the Takeover Plan (as appropriate) and place original on project file. | ||
Stakeholders
- IAD Project Team / Project Director
- NOD (Regional Office and Manager Technical Services)
- User/Sponsor
- CIOG
- Technical authorities
- EP&E (DEPI)
Related Reference Material
- Approved DBC
- Roles Plan
- Design Principles
- Commissioning and Handover Plan
- Contract with the Construction Contractor
- Contract with the CMC / CMS Contractor
- Contract with the GSS Contractor
- ECC, EMS, EMP and contamination close-out reports.