Acquisition
(Start Up)
4.2
In liaison with the project officer the Consultant will
be required to:
- Provide conceptual
design layouts of facilities options. Conceptual layouts
may be architectural or engineering in discipline, and
provide detail as required to explain the range of options
identified.
- Provide detailed
planning cost estimates of facilities options. Planning
cost estimates are required to provide an indication
of likely total construction costs and may include land,
infrastructure, energy, equipment, building fabric,
furniture and fittings and may include personnel costs.
The level of accuracy of estimates will vary depending
upon scope and complexity of project requirements.
- Prepare a Facilities
Acquisition Strategy (FAS). The FAS will detail the
method of procurement, the method of delivery, risks
(commercial, environmental, land, design, construction,
quality, policy) and budget for the facilities works.
Development of this document will require an understanding
of Commonwealth Procurement Guidelines and relevant
Departmental documentation.
- Prepare Functional
Design Briefs (FDBs). FDBs include a rigorous
analysis of spatial requirements, functional areas,
and include any special facilities requirements such
as technological, environmental, acoustic, land, equipment,
furniture and fittings.
- Prepare reports
and submissions for Government approval. These vary
but may include impact studies (economic, personnel
and facilities) point briefs, executive Summaries, discussion
papers etc.
- Prepare all
material required for referral to the Parliamentary
Standing Committee on Public Works (PWC), including:
- PWC referral
motion which is to include a letter to the Minister;
- notice of
the motion;
- the actual
motion; and
- the draft
media releases as required by the Public Works
Committee Act 1969.
- Prepare all
technical support material required as evidence for
PWC. The technical support material includes but is
not limited to:
- location
plans and maps;
- scope of
works;
- site description;
- zoning;
- planning
and design;
- project staging
plans;
- energy conservation
measures (including the use of solar energy);
- site planning;
- provision
for disabled;
- future development;
- structure;
- material
and finishes;
- mechanical
services;
- hydraulic
services;
- fire protection;
- electrical
and communications services;
- security;
- landscaping;
- civil works;
- authorities
consulted;
- relevant
codes and standards;
- project cost;
- construction
program; and
- associated
drawings.
- Attend as a
witness before the PWC. Provide public relations advice,
material and handling. Specialised PR/media skills are
required to advise on facilities related issues and
projects.
- Manage the
preparation of environmental and heritage assessments.
Specialised skills are required to provide detailed
reports incorporating all pertinent standards and legislation.
- Manage obtaining
necessary environmental and heritage approvals. Collating
and progressing facilities environmental and heritage
approvals through the relevant authorities.
- Provide specialised
facilities testing or investigatory services. These
may include engineering services, environmental investigatory
and reporting services, aircraft flight data modelling,
aircraft pavement analysis, acoustic services, and soils
analysis. Outcomes and recommendations to be reported
in the format as required.
|
|
Company |
Nominated
Point of Contact |
| APP
Corporation Pty Ltd |
Mac
Howell
Manager Defence Relations
Mail to:
PO Box 39
DEAKIN WEST ACT 2600
Located:
36 Thesiger Court
DEAKIN ACT 2600
Tel: 02 6285 1097
Fax: 02 6285 1153
Mob: 0412 369 302
Email: mac.howell@app.com.au |
| Halliburton
KBR Pty Ltd |
Rolfe
Hartley
Manager Civil Infrastructure
Mail to:
PO Box 5418
KINGSTON ACT 2604
Located:
Centenary House Level 3
19 National Circuit
BARTON ACT 2600
Tel: 02 62722722
Fax: 02 62722711
Mob: 0418 285 634
Email: Rolfe.Hartley@Halliburton.com |
| Carson
Group Pty Ltd |
Rod
Weir
Director
Level 4, 55 Chandos Street
ST LEONARDS NSW 2061
Mail to:
PO Box 333
ST LEONARDS NSW 1590
Tel: 02 9460 8470
Fax: 02 9460 8180
Mob: 0419 209 541
rweir@carsongrp.com.au |
| Connell
Wagner Pty Ltd |
Kevin Earle
Located:
Level 1, 31 Thesiger Crt
DEAKIN ACT 2614
Tel: 02 6232 5138
Fax: 02 6232 5151
Mob: 0408 655 549
Email: earlek@conwag.com.au |
| Gutteridge
Haskins & Davey Pty Ltd |
David
Buckley
Principal Engineer
Mail to:
PO Box 36
BELCONNEN ACT 2616
Located:
Level 2, Belconnen Chambers
59 Cameron Avenue
BELCONNEN ACT 2617
Tel: 02 6245 1923
Tel: 02 6253 1999
Fax: 02 6253 1911
Mob: 0402 257 677
Email: david_buckley@ghd.com.au |
| Power
Initiatives and Bligh Voller Nield |
Mark
Power
PO Box 346
FYSHWICK ACT 2609
Tel: 02 6239 1740
Fax: 02 6239 1786
Mob: 0417 240 976
Email: canberra@powerinit.com.au |
| Savant
Pty Ltd, Rider Hunt Group, CMR Pty Ltd, and Righter
& Associates |
Cambell
Mackie
Managing Director
Level 1, 77 Grenfell St
ADELAIDE SA 5000
Tel: 08 8228 8100
Fax: 08 8228 8188
Mob: 0408 823 170
Email: cmackie@savant.com.au |
| Special
Project Management Pty Ltd |
John
Lines
PO Bax 258
GUNGAHLIN ACT 2912
Tel: 02 6262 2836
Fax: 02 6262 2837
Email: jlines@pcug.org.au |
| Woods
Bagot |
Peter
Hoskins
Manager Strategic Planning and Project Management
Mail to:
PO Box N19
Grosvenor Place
SYDNEY NSW 2000
Located:
Level 10, Wynyard Green
11-31 York St
SYDNEY NSW 2000
Tel: 02 9249 2500
Fax: 02 9299 5592
Mob: 0417 000 014
Email: peter.hoskins@woodsbagot.com.au |
Acquisition
(Project Management)
Panel
Members
In
liaison with the project officer the Consultant will be
required to:
Time Management
- The Consultant
is to prepare, maintain and operate a Master Time Program
for the project.
- The Consultant
is to ensure all other programs used on the project
remain consistent with Master Time Program.
- The Consultant
is to ensure the Master Time Program allows sufficient
lead times for any staff relocation activities associated
with the project.
- The Consultant
is to review and approve Time Programs submitted by
the design Consultant and construction contractors (subordinate
programs) for their components of the project. In reviewing
those programs, the Consultant must ensure they adequately
reflect the requirements of the Master Time Program
and are sufficiently detailed to consider all activities,
including approval times, major supply item lead times
and co-ordination requirements.
- The Consultant
is to monitor the Master Time Program for the project
to ensure the requirements of the Department of Defence
are met. In monitoring the Master Time Program, the
Consultant is to ensure the subordinate programs are
being adequately maintained.
Cost Management
- The Consultant
is to prepare, maintain and operate a Cost Control System
for the project. The Cost Control System is to be of
sufficient detail to provide accurate assessments of
the projects financial status at any point in
time. The Cost Control system must include all aspects
of the project and show links between all stages. The
Cost Control System must also take into account any
internal Defence financial management systems (eg. ROMAN).
- The structure
and format of reports generated by the Cost Control
system is to be approved by the project officer.
- The Cost Control
system is to allow accurate tracking of:
- cash flows;
- contingency
planning and monitoring;
- Purchase
Orders;
- Variations;
and
- commitments
and expenditure.
- The Consultant
is to report to the Department of defence as soon as
it becomes aware that the approved budget may be exceeded
and must provide its recommendations as to the appropriate
action to be taken by the Department of Defence. The
recommendation is to include a full impact statement
of the mechanisms necessary to ensure the approved budget
will not be exceeded.
Risk
Management
- The Consultant
is to prepare, maintain and operate a Risk Management
Program for the Project. The Risk Management Program
is to be used by the Consultant to identify, monitor
and undertake actions to mitigate all risks associated
with the project so the project objectives are achieved.
Specific
Tasks Related to the Assessment of Packaging Options
- The Consultant
is to evaluate the packaging options and contract types
to be used for each construction package of the Project
(as reflected in the Facilities Acquisition Strategy).
The evaluation is to assess and recommend to Defence
the optimal packaging option that ensure the project
objectives are met and there is minimal disruption to
the Base operations.
- The
Consultant is to prepare for, organise and facilitate
a Value Management Review (VMR) of the FDB and preliminary
sketch plans for each construction package. The VMRs
are to be undertaken at a time recommended by the Consultant.
Each VMR is to validate, or revise as appropriate, early
concepts for the package, including the Cost/Benefit
study. In the context of the project, prepare for and
facilitate means providing all material, the location,
facilitation service, reporting services and facilities
for the conduct of the VMR.
Construction
Co-ordination
- The Consultant
is to prepare a Work Plan (WP) for each stage setting
out (as appropriate):
- proposed
relocation of individual user groups;
- changes to
pedestrian and vehicular systems;
- changes to
parking facilities;
- temporary
and permanent changes to provision of utilities;
- location
of areas for construction activities;
- processes
for minimising foreign object debris;
- impact of
construction activities on Defence activities, such
as air traffic movement;
- measure to
comply with environmental and heritage requirements;
- condition
required for each facility which is to be handled
over to a Construction Contractor;
- date for
handover of such facilities; and
- such other
matters as are directed by the project officer.
- The Consultant
is to obtain the project officers approval to
the WP within 21 days of the Consultant being notified
of approval of a stage of the project.
- Any change
to the WP must be approved by the project officer.
- The Consultant
must ensure that all construction and related activities
are carried out in accordance with the approved WP.
- The Consultant
must regularly notify the project officer of the date
by which facilities are to be handed over to Construction
Contractors. The method and timing of notification is
to be approved by the project officer and must take
into account the time required by the Department of
Defence for relocation and handover.
Selection
of Consultants and Contractors
- The Consultant
is to prepare any Tender Evaluation Plans (TEP) for
the selection of Consultants and contractors.
- The Consultant
is to prepare documentation needed for the calling of
all Invitations to Register Interest (ITR) and Requests
for Tender (RFT) for the selection of all other Consultants
and contractors required to deliver the project.
- The Consultant
is to:
- Prepare all
documentation necessary to call for ITRs;
- Prepare advertisements
for the ITRs;
- Place the
advertisements for the ITRs;
- Prepare and
distribute the ITR packages to all firms requesting
such information;
- Issue any
addenda as may be required;
- Prepare for
and participate in a Registration Evaluation Board in
a manner approved by the Department of Defence that
assesses the ITRs received, and includes:
- Validation
of ITRs;
- Evaluation
of ITRs;
- Carrying
out reference checks;
- Arranging
for financial assessment of ITRs (if considered necessary);
and
- Participating
in interviews with firms (if considered necessary);
- Prepare a
report summarising the findings of the Registration
Board as to firms to be invited to tender for the
activities associated with the ITR.
- Preparing
a report summarising the findings of the Registration
Board as to firms to be invited to tender for the
activities associated with the ITR.
- Preparing
tender documentation, arranging for review by Department
of Defence legal advisers if required by the project
officer, and distributing to all tenders.
- Preparation
and distribution of any addenda as may be required;
- Participating
in and supporting the Tender Evaluation process including:
- Validation
of tenders;
- Review of
tenders;
- Evaluation
of tenders;
- Carrying
out reference checks;
- Carrying
out financial assessments of tenderers;
- Arrange and
manage interviews with tenderers;
- Analysis
of alternatives or substitutions proposed by tenderers
including any detailed investigations in conjunction
with tenderers enabling the Department of Defence
to make an informed decision on whether to proceed
with an alternative proposal and if so, to enable
the alternative to be fully specified in the contract
documentation;
- Preparation
of a report for Defence approval recommending a preferred
tender for the Consultants and/or Contractors needed
to deliver the project;
- Manage and
participate in any negotiations with tenderers;
- Assist the
project officer to award the contract to the successful
Tenderer, including:
- Notification
of contract award;
- Preparation
and distribution to the Contractor, on behalf of the
Department of Defence, of a notice to proceed with
the work; and
- Assist the
Department of Defence legal advisers in the preparation
and distribution of sets of contract documents for
execution by parties to the contract.
Specific
Tasks in relation to the Design of Facilities
- The Consultant
is to determine the most appropriate times for the conduct
of design reviews and advise all necessary parties of
the design reviews.
- The Consultant
is to facilitate all design review. The design reviews
must ensure the design by all disciplines is consistent
and in accordance with the agreed project FDB, approved
budget, all known environmental and heritage conditions
and is consistent with the building Code of Australia,
State and Territory Building Regulations, Acts, ordinances,
Defence Accommodation Guidelines, the Facilities Manual,
FACMAN 2, and the Security Manual.
- The Consultant
is to ensure that appropriately qualified designers
certify all designs.
- The Consultant
is to ensure Certificates of Compliance in relation
to the fire and safety components of the designs are
provided by all design Consultants for all appropriate
building works. The certificates are to be provided
by a registered building surveyor.
Quality
Management
- The Consultant
is to develop a Project Quality Plan (PQP) for the project
to facilitate delivery of all aspects of the project
(including the rectification of defects) in the agreed
time frame and to the required quality. The PQP must
be based on AS/NZS ISO 9001 : 1994 and must cover all
Services provided under this Contract. The PQP must
make appropriate provision to monitor the quality plans
of each Consultant and contractor engaged on the project,
and integrate these quality aspects.
- The Consultant
is to ensure that:
- The PQP identifies
all obligations and responsibilities held by the Consultant;
- The PQP assigns
responsibility to achieve the project objectives;
- The PQP provides
a tracking mechanism to allow the status of the project
to be identified at any stage during the project;
- The PQP links
to the quality systems of other Consultants and contractors
involved in the project, integrating them in such
a manner that the overall quality system is a co-ordinated
tool used to assist the delivery of the project.
- The Consultant
is to submit the PQP to the Department of Defence for
approval by the project officer within 14 days of notification
of acceptance of the offer. Acceptance by the project
officer does not absolve the Consultant of any responsibilities
in relation to the delivery of the project.
- The Consultant
is to maintain and operate the quality system throughout
the entire project, ensuring the quality system assists
in delivering the project objectives.
- The Consultant
is to review and approve the adequacy of PQPs submitted
by all Design Consultants and Contractors involved in
the project. This review must ensure the PQPs developed
by each Design Consultant or Contractor are not inconsistent
with the Consultants PQP.
- The Consultant
is to plan and develop a schedule for the review of
quality systems operated by all Design Consultants and
Contractors involved on the Project. The schedule is
to be submitted to the project officer for approval.
- The Consultant
is to audit the implementation of all Consultants
and construction contractors quality systems in
accordance with the approved schedule.
- evelopment and operation of their quality systems.
Specific
Tasks in relation to the Construction of Facilities
The
Consultant is to establish and facilitate a partnering workshop
for the project. In establishing the partnering workshop,
develop a partnering strategy that will apply to the project.
Obtain approval for the partnering approach from the project
officer.
The
Consultant is to prepare the necessary Soil and Water Management
Plans for the site.
The
Consultant is to administer all contracts associated with
the project so that the project objectives are achieved.
In administering the contracts, the Consultant must provide
the Department of Defence with a full impact report on any
matter relating to:
Cost;
Quality;
Variations;
or
Defects.
The
impact report is to provide an assessment of the impact
on the Master Time Program, Cost Program or quality system,
as appropriate. The report is to also recommend actions
needed to be taken to ensure the approved program and budget
are not exceeded.
The Consultant
is to supervise all construction to ensure all works are
constructed in accordance with approved designs and specifications,
and that these construction activities are built using commonly
accepted industry standards.
The
Consultant is to manage all project construction sites so
that all OH&S requirements are met.
The
Consultant is to manage all project construction sites so
that the WP is adhered to.
The
Consultant is to manage all project construction sites so
that industrial harmony is maintained on the site.
The
Consultant is to manage all project construction sites so
that the Defence Installation remains operational, paying
particular attention to debris, pedestrian and vehicle traffic,
waste disposal, continuity of utilities (including power,
lighting, sewer, water, gas and compressed air).
The
Consultant is to arrange and conduct all site meetings needed
to deliver the project.
The
Consultant is to minute all meetings, allocate responsibility
for action, and monitor all actions arising from meetings
to ensure those organisations or individuals responsible
for actions undertake the appropriate actions.
The Consultant
is to regularly inspect the works and obtain certifications
that construction has been carried out in accordance with
approved plans and specifications. The Consultant is to
determine the most appropriate organisation to provide the
certification, based on common industry practice.
The
Consultant is to ensure all necessary sign-offs are received.
The
Consultant is to prepare the following final reports for
each project package:
Performance
report of the Design Consultant;
Performance
report of the Contractors; and
Project
completion report addressing the overall delivery of the
package.
The
Consultant is to provide to the project officer at Practical
Completion of each separable part, the copies of consolidated
manuals for operation and maintenance of all mechanical
and electrical plant items at each site specified in the
contract. Copies of As Constructed drawings
are to be obtained from the contractor and provided to Defence.
As Constructed site survey drawings are to be
provided to Defence in accordance with the appropriate survey
specifications.
The
Consultant is to develop and manage Method of Work Plan
(MOWP) for airfield works.
The Consultant
is to support the project officer in developing strategies
and documentation for any ongoing maintenance requirements
associated with the project.
Progress
Reporting
The
Consultant is to prepare monthly reports to the project
officer as to the progress of the project. Those reports
must, as a minimum, address the following issues:
Progress
towards achieving Project objectives;
Time
performance;
Financial
performance;
Quality
performance;
Design
and construction progress;
Design
and construction issues;
WP
issues;
Impending
relocations, and the notification given;
Impact
of the future works on base operations;
Photographic
record of works of each component; and
OH&S
and IR issues.
The
Consultant is to attend all design co-ordination meetings.
The
Consultant is to attend, provide briefings and prepare the
minutes for Project Control Group meetings.
Problem
Log
The
Consultant is to maintain a log of all problems or issues
arising during all phases of the project. The log shall
include:
A unique
identifier for the problem;
The
date the problem arose;
A description
of the problem;
A description
of the proposed solution;
The
identity of the organisation/person assigned to undertake
the identified solution;
The
target date for resolution of the problem;
The
current status of the problem resolution, using a status
agreed by the project officer; and
The
actual date the problem was resolved.
Management
of Defects
The
Consultant is to assess any defect that becomes apparent
during the defects liability period.
If
required as a result of any assessment undertaken during
the defects liability period, the Consultant is to arrange
for and inspect the rectification of the defect by the Contractor.
The
Consultant is to continue to manage the project until all
defects have been rectified under all packages, the last
Defects Liability Period has expired, and all claims or
disputes are finalised.
The Consultant
is to prepare a Post Occupancy Evaluation Report at the
end of the Defects Liability Period.
The
Consultant is to assist the Department of Defence in any
dispute that arises in respect of any contract.
The
Consultant is to prepare a detailed Completion Report to
finalise all contract invoicing claims for payment and contractual
administration matters.
Contract
Administration
After
the award of the Construction Contract the Consultant will
perform and discharge the functions imposed upon the party
defined as either the Superintendent, Project Consultant
or the Contract Administrator in the Construction Contract.
In particular (but without limitation), the Consultant shall
provide appropriate advice and information to the Department
of Defence and ensure that the Contractor discharges its
duties and obligations in relation to the construction and
commissioning of the project in accordance with the Construction
Contract.
Note:
This menu of tasks will be refined from time to time to
take account of better ways of delivering projects and the
differences in the delivery frameworks supporting the Defence
Suite of Contracts.
|
Acquisition
Panel - Project Management |
| Company |
Nominated
Point of Contact |
| APP
Corporation Pty Ltd |
Mac
Howell
Manager Defence Relations
Mail to:
PO Box 39
DEAKIN WEST ACT 2600
Located:
36 Thesiger Court
DEAKIN ACT 2600
Tel: 02 6285 1097
Fax: 02 6285 1153
Mob: 0412 369 302
Email: mac.howell@app.com.au |
| Halliburton
KBR Pty Ltd |
Rolfe
Hartley
Manager Civil Infrastructure
Mail to:
PO Box 5418
KINGSTON ACT 2604
Located:
Centenary House Level 3
19 National Circuit
BARTON ACT 2600
Tel: 02 62722722
Fax: 02 62722711
Mob: 0418 285 634
Email: Rolfe.Hartley@Halliburton.com |
| Carson
Group Pty Ltd |
Rod
Weir
Director
Mail to:
PO Box 333
ST LEONARDS NSW 1590
Located:
Level 4, 55 Chandos Street
ST LEONARDS NSW 2065
Tel: 02 9460 8470
Fax: 02 9460 8180
Mob: 0419 209 541
rweir@carsongrp.com.au |
| Connell
Wagner Pty Ltd |
Kevin
Earle
Located:
Level 1, 31 Thesiger Crt
DEAKIN ACT 2614
Tel: 02 6232 5138
Fax: 02 6232 5151
Mob: 0408 655 549
Email: earlek@conwag.com.au |
| Gutteridge
Haskins & Davey Pty Ltd |
David
Buckley
Principal Engineer
Mail to:
PO Box 36
BELCONNEN ACT 2616
Located:
Level 2, Belconnen Chambers
59 Cameron Avenue
BELCONNEN ACT 2617
Tel: 02 6245 1923
Tel: 02 6253 1999
Fax: 02 6253 1911
Mob: 0402 257 677
Email: david_buckley@ghd.com.au |
| Savant
Pty Ltd, Rider Hunt Group, CMR Pty Ltd, and Righter
& Associates |
Cambell
Mackie
Managing Director
Level 1, 77 Grenfell St
ADELAIDE SA 5000
Tel: 08 8228 8100
Fax: 08 8228 8188
Mob: 0408 823 170
Email: cmackie@savant.com.au |
| Woods
Bagot |
Peter
Hoskins
Manager Strategic Planning and Project Management
Mail to:
PO Box N19
Grosvenor Place
SYDNEY NSW 2000
Located:
Level 10, Wynyard Green
11-31 York St
SYDNEY NSW 2000
Tel: 02 9249 2500
Fax: 02 9299 5592
Mob: 0417 000 014
Email: peter.hoskins@woodsbagot.com.au |
|
|