| Activity | Considerations | Outcome |
|
1) Defence Project Officer (DPO) or delegated Project Contractor fills in the Considerations Matrix in consultation with identified regional and technical authorities.
|
As the name suggests, the Considerations Matrix is a comprehensive list of potential risks, or issues that are to be considered for each siting option. The aim is to assist in establishing the suitability of each siting option with respect to the various aspects of the project. It is not anticipated that all listed considerations will necessarily be relevant to all of the siting options. The filling out of the Matrix is the responsibility of the Defence Project Officer however the Project Contractor may assist with this process. The DPO or delegated contractor is expected to have the requisite technical expertise to decide which considerations are likely to be of relevance. Where uncertainty exists as to the relevance of a consideration, Regional and Technical Authorities should be contacted for guidance. It is not necessary to contact an authority if a consideration is clearly not relevant to a potential siting option. When filling in the Matrix the DPO or contractor should include the name of the authority providing the advice and the date. N.B. Activity 1 in Step 8 is only required if the DPO or contractor has not consulted a regional or technical authority in completing a relevant consideration. An authority point of contact for each consideration in the Matrix is listed below. |
The Considerations Matrix is completed for each siting option.
|
Consideration Regional and Technical Authority Tab 1 Technical Considerations Relating to Airfields and Aviation Activities Obstruction Clearance SurfacesLand Planning and Spatial Information (DLPSI)
Contact: EO LUP Gary Lee
Ph: 02-62668187
Email: gary.lee1@defence.gov.au Obstruction Lighting and Marking RequirementsLand Planning and Spatial Information (LPSI)
Contact: EO LUP Gary Lee
Ph: 02-62668187
Email: gary.lee1@defence.gov.au Air Traffic Control (ATC) Tower/Fire Station Line of SightBase Commander
Exhaust PlumesLand Planning and Spatial Information (LPSI)
Contact: EO LUP Gary Lee
Ph: 02-62668187
Email: gary.lee1@defence.gov.au Aircraft NoiseLand Planning and Spatial Information (LPSI)
Contact: EO LUA Erwin Wegner
Ph: 02-62668124
Email: erwin.wegner@defence.gov.au Environmental Considerations Regional Environmental Officer (REO) Tab 2 Electromagnetic Radiation and Noise ConsiderationsElectromagnetic Radiation
- Fuel Facilities
Directorate of Estate Engineering Policy (DEEP)
Contact: TBA
- Explosive Ordnance Facilities
Guided Weapons Explosive Ordnance Branch
Contact: Barry Lock
E-mail: barry.lock@defence.gov.au
- Navigation Aids
- Microwave Link Paths
- Radio Communications
Ground Telecommunications Equipment Systems Project Office (GTESPO)
Contact: Noel Marriot
Ph: 02-49645561
E-mail: noel.marriott@defence.gov.au
- Minimum Separation Distances
- RADHAZ Safety Areas
Regional Occupational Health & Safety Manager
(ROHSM or ROHSCO)
and
Occupational Health Safety & Conditions Branch (OHSC)
Contact: Kevin Brett
Ph:02-61272012
E-mail: kevin.brett@defence.gov.au Noise and VibrationTBA
Tab 3 Master Planning ConsiderationsInternal Considerations Land Planning and Spatial Information (LPSI)
NSW/ACT/SA/VIC/NT-K/WA/QLD/TAS
Contact: Judith Bedford
Ph: 02-62668321
E-mail: judith.bedford@defence.gov.auMaster Plan Land Planning and Spatial Information (LPSI)
NSW/ACT/SA/VIC/NT-K/WA/QLD/TAS
Contact: Judith Bedford
Ph: 02-62668321
E-mail: judith.bedford@defence.gov.au Tab 4 Environment and Heritage ConsiderationsEnvironment and Heritage Regional Environmental Officer (REO)
Estate Policy & Environment Branch Tab 5 Engineering ConsiderationsLocation and Capacity of Hydraulic Services
- Water
- Sewer
- Stormwater
- Substation
- ICT
Regional Planning Manager (RPM)
Regional Planning Manager (RPM)
Regional Planning Manager (RPM)
Regional Planning Manager (RPM)
Regional Information Communication Technology Manager (RICTM)
- Fuel Installations
Directorate of Estate Engineering Policy (DEEP)
Contact: TBA Tab 6 Design Traffic and Property Considerations
- Aircraft/vessel/vehicles involved with new facility
Directorate of Estate Engineering Policy (DEEP)
Contact: SQNLDR Danny Cusack
Ph: 02-62668183
E-mail: danny.cusack@defence.gov.au
- Traffic Considerations
- Non-Defence Tenants
Regional Development Manager (RDM)
Regional Development Manager (RDM) Tab 7 Security and Safety Considerations
- Security Considerations
Regional Security Manager/Base Commander/Defence Security Authority
- Explosive Ordnance Safeguarding
Base Armaments Manager (BAM)
Directorate of Explosive Ordnance Services (DEOS)
Contact: Simon Gibbons
Ph: 02-47370011
E-mail: simon.gibbons@defence.gov.auDirectorate of Estate Engineering Policy (DEEP)
Contact: SQNLDR Danny Cusack
Ph: 02-62668183
E-mail: danny.cusack@defence.gov.au
- Electromagnetic Radiation
Regional Occupational Health & Safety Manager
(ROHSM or ROHSCO)
Occupational Health Safety & Conditions Branch (OHSC)
Contact: Kevin Brett
Ph:02-61272012
E-mail: kevin.brett@defence.gov.au