Site
Selection FULL REVIEW Step 7 - Fill
in the Considerations Matrix |
||
| Activity | Considerations | Outcome |
|
1) Defence Project Officer (DPO) or delegated Project Contractor fills in the Considerations Matrix in consultation with identified Subject Matter Experts.
|
As the name suggests, the Considerations Matrix is a comprehensive list of potential risks, or issues that are to be considered for each siting option. The aim is to assist in establishing the suitability of each siting option with respect to the various aspects of the project. It is not anticipated that all listed considerations will necessarily be relevant to all of the siting options. The filling out of the Considerations Matrix is the responsibility of the Defence Project Officer, however the Project Contractor (eg PM/CA) may assist with this process. The DPO or delegated contractor is expected to have the requisite technical expertise to decide which considerations are likely to be of relevance and to complete the information requested as far as practicable. Where uncertainty exists as to the relevance of a consideration, subject matter experts (SME) should be contacted for guidance and to assist in filling in the required information. It is not necessary to contact an authority if a consideration is clearly not relevant to a potential siting option. A subject matter expert point of contact for each consideration in the Considerations Matrix is listed below. |
The Considerations Matrix is completed for each siting option.
|
Consideration
|
Subject Matter Expert |
|
Tab 1 Technical Considerations Relating to Airfields and Aviation
Activities |
|
|
Obstruction Clearance Surfaces |
Land
Planning and Spatial Information (DLPSI) |
| Obstruction Lighting and Marking Requirements |
Land Planning
and Spatial Information (LPSI) |
| Air Traffic Control (ATC) Tower/Fire Station Line of Sight |
Senior Air Traffic Controller (SATCO) |
|
Exhaust Plumes |
Land
Planning and Spatial Information (LPSI) |
| Aircraft Noise |
Land
Planning and Spatial Information (LPSI) |
|
Environmental Considerations |
Regional Environmental Officer (REO) |
|
Tab
2 Electromagnetic Radiation and Noise Considerations
|
|
|
Electromagnetic Radiation
|
Directorate of Estate Maintenance Policy |
|
Directorate of Ordnance Safety Land Engineering Agency |
|
Ground
Telecommunications Equipment Systems Project Office (GTESPO) Contact: Noel Marriot Ph: 02-49645561 E-mail: noel.marriott@defence.gov.au |
|
Regional
Occupational Health & Safety Manager (ROHSM or ROHSCO) and Directorate of Radiation Hazard Management Contact: Kevin Brett Ph:02-62662769 E-mail: kevin.brett@defence.gov.au |
| Noise and Vibration |
TBA |
|
Tab
3 Master Planning Considerations |
|
| Internal (on base) Considerations |
Land Planning and Spatial Information (LPSI) Zone Planning and Master Planning |
|
Tab
4 Environment and Heritage Considerations |
|
| Environment and Heritage | Regional Environmental Officer (REO) Estate Policy & Environment Branch |
|
Tab
5 Engineering Considerations |
|
|
Location and Capacity of Hydraulic Services |
|
|
Base Services Manager (BSM) |
|
Base Services Manager (BSM) |
|
Base Services Manager (BSM) |
|
Base Services Manager (BSM) |
|
Regional Information Communication Technology Manager (RICTM) |
|
Directorate
of Estate Engineering Policy (DEEP) Contact: TBA |
|
Tab
6 Design Traffic and Property Considerations |
|
|
Directorate
of Estate Engineering Policy (DEEP) Contact: SQNLDR Dave Alder Ph: 02-62668183 E-mail: david.alder@defence.gov.au |
|
Base Services Manager (BSM) Base Services Manager (BSM) |
|
Tab
7 Security and Safety Considerations |
|
|
Regional Security Manager/Base Commander/Defence Security Authority |
|
Base
Armaments Manager (BAM)
Directorate of Explosive Ordnance Services (DEOS) |
|
Regional
Occupational Health & Safety Manager Directorate of Radiation Hazard Management |