Phase 1 Replacement Refuelling Trucks
This phase is intended to enhance or replace the existing ADF aviation ground refuelling capability, including vehicles and hydrant carts, within the National Support Base.
This project seeks to modernise and replace the current ADF aviation ground refuelling equipment fleet, including vehicles and hydrant carts, ensuring sustainment of all current and future ADF fixed and rotary wing aircraft fleets.
The likely acquisition strategy is not clear at this stage but depending on the maturity of systems within the market, the procurement may consider one of the following or a combination:
Depending on the procurement (ADF ownership or lease) strategy, the through-life support concept for this project will consider supportability options for fleet management, repair and maintenance, storage and distribution, provision of technical data and training as a minimum. It also sees use being made of current in-service capacity and facilities, or original equipment manufacturer support or a combination of both. Contracts for such support will generally be considered at the same time as acquisition.
Capabilities and related activities that may provide opportunities for Australian industry in this phase include:
| Activity | Capability |
|---|---|
| Aviation Ground Support Equipment | |
| Assemble / Install | D |
| Design | O |
| Education / Training | O |
| In-Service / Through-life Support | O |
| Logistics Support | O |
| Manufacture / Construct | O |
| Refurbish / Upgrade | O |
| Repair and Maintain | O |
| Systems Integration | O |
| Test and Evaluate | O |
| ACAT Attribute | Complexity Level Assessment |
|---|---|
| Acquisition Cost | Level 3 Moderate $100m–$500m (Towards the lower end of the band) |
| Project Management Complexity | Level 3 Moderate |
| Schedule | Level 4 Low |
| Technical Difficulty | Level 4 Low |
| Operation and Support | Level 4 Low |
| Commercial | Level 4 Low |
The ACAT Level assessed for this Phase is ACAT III.
| First Pass Approval | FY 2011-12 to FY 2012-13 |
|---|---|
| Year-of-Decision | FY 2013-14 to FY 2015-16 |
| Initial Operating Capability | 2016 to 2018 |
Capability Staff:Staff Officer Joint Theatre Distribution (02) 6265 4934 |