The table below shows changes made to the Public DCP 2009 projects as at 31 December 2009 including First Pass Approvals.

Proposal Number Phase Description
AIR 5416 4B2 Project entry updated to reflect approval of Phase 4B1, and Phase 4B2 consideration deferred to align with the anticipated availability of technology
AIR 5428 1 Project entry updated to show First Pass Approval achieved
AIR 6000 2A/2B Project entry rewritten to reflect revised acquisition strategy and approval of the acquisition of the first 14 aircraft
AIR 8000 1 Phase 1 consideration deferred to better align with other capability priorities
AIR 9000 Overview Updated to reflect deletion of SCAP 2
AIR 9000 Ph 5C Phase 5C will be considered earlier than previously planned
AIR 9000 SCAP 1 Updated to reflect deletion of SCAP 2
JP 2008 5B Phase 5B will be considered earlier than previously planned
JP 2047 3 Phase 3 will be considered earlier than previously planned
JP 2080 2B.1 Phase 2B.1 will be considered earlier than previously planned
JP 2089 3 Project entry amended to reflect approval of Phase 2B
JP 2096 1 Project consideration deferred
JP 2110 1B Project entry updated to reflect approval of Phase 1A
LAND 17 1B and 1C Project entry revised to show separate phases
LAND 75 4 Project entry updated to reflect approval of Phase 3.4
LAND 112 4 Phase 4 will be considered earlier than previously planned
LAND 125 3B Project entry updated to reflect approval of Phase 3A and Phase 3B consideration deferred because rapid acquisition has satisfied immediate requirements
LAND 146 2 Project consideration deferred to align with anticipated availability of technology
SEA 1397 5B Project entry updated to reflect approval of Phase 5A.
SEA 1442 4 Phase 4 will be considered earlier than previously planned

Deleted projects

Proposal Number Phase Description
AIR 9000 SCAP 2 Seahawk Capability Assurance Program 2 deleted due to programmed replacement of the Seahawk fleet as a matter of urgency under AIR 9000 Phase 8
JP 2070 4 AP-3C Light Weight Torpedo Integration deleted due to assessment that existing torpedo’s capability is adequate and the planned replacement of the AP-3C platform under AIR 7000 Phase 2B