TABLE OF CONTENTS
Paragraph
- Chapter 1 Overview
-
Preface 1.1
Introduction 1.2
Departmental Authority 1.3
Criteria Objectives 1.4
The Criteria Concept 1.5
Managements Data Needs 1.6
Performance Reporting 1.7
Implementation Process Summary 1.8
- Chapter 2 General Information
-
Terms Explained 2.2
Criteria Requirements 2.3
- Chapter 3 Organisation
-
Introduction 3.1
Contract Work Breakdown Structures 3.2
Interrelationship of CWBS and Organisation 3.3
Cost Accounts 3.4
Types of Effort - Differentiation 3.5
Work Packages 3.6
Level of Effort 3.7
Apportioned Effort 3.8
Detailed Planning 3.9
Criteria 3.10
- Chapter 4 Planning and Budgeting
-
Introduction 4.1
Planning 4.2
Scheduling 4.3
Budgeting 4.4
Management Reserve 4.5
Undistributed Budgets 4.6
Contract Budget Base 4.7
Price and Exchange Variation 4.8
Performance Measurement Baseline (PMB) 4.9
Criteria 4.10
- Chapter 5 Accounting
-
Introduction 5.1
Material Accounting System 5.2
Criteria 5.3
- Chapter 6 Indirect Cost Management
-
Introduction 6.1
Criteria 6.2
- Chapter 7 Analysis
-
Introduction 7.1
Budgeted Cost for Work Scheduled 7.2
Budgeted Cost for Work Performed 7.3
Data Analysis 7.4
Data Summarisation 7.5
Significant Variances 7.6
Technical Achievement 7.7
Estimate at Completion 7.8
Criteria 7.9
- Chapter 8 Revisions and Access to Data
-
Introduction 8.1
Contract Changes 8.2
Approval 8.3
Formal Reprogramming 8.4
Baseline Maintenance 8.5
Access to Data 8.6
Criteria 8.7
- Chapter 9 Implementation Processes
-
General 9.1
Pre-Contract Activities 9.2
Contracts 9.3
Review Teams 9.4
Demonstration Process 9.5
Compliance After Acceptance 9.6
- Chapter 10 CSCSC and Work Teams
-
Work Teams 10.1
Cost Performance Reporting 10.2
- Chapter 11 Additional Considerations for Production/Manufacturing Contract Applications
-
Introduction 11.1
Cost Accounts for Manufacturing 11.2
Manufacturing Work Packages 11.3
Considerations 11.4
- Chapter 12 Reporting
-
General Requirements 12.1
- Chapter 13 Surveillance
-
Purpose 13.1
Concepts 13.2
Administrative Aspects 13.3
Deviations 13.4
Subcontractors 13.5
Surveillance Personnel 13.6
Records and Reports 13.7
Responsibilities 13.8
Planning and Performing Surveillance 13.9
Surveillance During Phase I 13.10
Surveillance During Phase II 13.11
- ANNEXES
-
A. Example of CSCSC Request for Tender and Contract Requirements
B. Example Memorandum of Understanding for CSCSC
C. CSCSC Negotiation Checklist
D. Evaluation/Demonstration Review Checklist for CSCSC
E. Evaluation/Demonstration Review Worksheet Formats
F. CSCSC Review Reports
G. Sample Cost Performance Report Formats
H. List of Abbreviations
Index