A1. The Defence Purchasing Manual (DEFPUR 101) contains standard clauses concerning
CSCSC that may be included in RFTs and Contracts when required. Samples of the
relevant clauses are shown below.
REQUEST FOR TENDER CLAUSES.
7.8 Cost Schedule Control System (Optional Clause)
7.8.1 The successful tenderer will be required to maintain and use a Cost
Schedule Control System (CSCS) within the contract price in accordance with
Clause 12.4 in the draft Contract. For the purposes of evaluation tenderers
are to submit with their tenders information detailing and/or substantiating
a description of the general organisation, management and procedures designed
to comply with the specified CSCS standards.
7.8.2 Tenderers are required:
a. to submit at Annex C, DID 029, a declaration that all existing management
procedures have been examined by tenderers to establish their suitability for
meeting the Cost Schedule Control requirements contained within this Request
for Tender; and
(i) if the existing system is found to be suitable, tenderers provide a declaration
that the existing system complies with the requirements; or
(ii) if shortcomings are found in the existing procedures, tenderers are to
document such shortcomings and provide details of proposed corrective action;
and
b. to submit to an assessment by the Commonwealth, on site if necessary, of
their Cost Schedule Control System for compliance with, or potential to comply
with, the specified standards as part of the tender evaluation.
7.9 Contract Work Breakdown Structure (CWBS) (Optional Clause)
7.9.1 The successful tenderer will be required to comply with principles set
forth in the version current at the Effective Date of US MIL-STD-881, Work Breakdown
Structures For Defense Materiel Items. Tenderers are to propose at Annex C,
DID 030, a preliminary CWBS based on the summary Work Breakdown Structure detailed
in the Statement of Requirement. Tenderers shall extend this summary WBS in
as much detail as necessary to identify the structure of the work effort to
successfully achieve the end objective of the contract."
DRAFT CONTRACT CLAUSES.
12.4 Cost Schedule Control System (Optional Clause)
12.4.1 Within the period specified in the Contract Schedule, the Contractor's
Cost Schedule Control Systems meet, and thereafter continue to meet, Australian
Cost Schedule Control Systems Criteria DEF(AUST)5655. The processes described
in the Australian Cost Schedule Control Systems Implementation Guide, DEF(AUST)5657
for the review and acceptance of the Contractor's Cost Schedule Control Systems
are followed by the parties.
12.4.2 The Contractor facilitates surveillance of its Cost Schedule Control
Systems in accordance with the Australian Cost Schedule Control Systems Implementation
Guide, DEF(AUST)5657.
12.5 Contract Work Breakdown Structure (CWBS) (Optional Clause)
12.5.1 The Contractor complies with the principles set forth in the version
current at the Effective Date of US MIL-STD-881 Work Breakdown Structure (WBS)
For Defense Materiel Items. The summary WBS detailed in the Statement of Work
and Dictionary form the basis for preparation of the CWBS by the Contractor.
12.5.2 The Contractor:
a. within 60 days of the Effective Date, extends the summary WBS in as much
detail as necessary to identify the structure of the work effort and define
Cost Accounts; and
b. within 120 days of the Effective Date, extends the summary WBS in as much
detail as required to define the work effort necessary to successfully achieve
the end objective of the Contract.
12.5.3 On approval of the CWBS by the Project Authority, it;
a. is used by the Contractor as the framework for Contract planning, management
and status reporting, and for estimating cost, schedule and technical achievements;
b. describes its elements in a CWBS Dictionary and Index which have specific
identification to discrete items of the Supplies and any specification(s) contained
in the Statement of Work; and
c. is used in production of the Supplies and represents all the Contractor's
costs.
12.5.4 The Contractor identifies subcontractor activities in a WBS separate
from, but integrated into and identifiable within, the CWBS.
12.5.5 Prior approval to change to CWBS is not required for elements below
the reporting level provided the Project Authority is notified within 60 days
of the changes being made, and the changes are consistent with the summary WBS
and US MIL-STD-881.
12.5.6 The Dictionary for the CWBS is progressively expanded by the Contractor
as required for the management of the work under the Contract. Lower levels
of the CWBS are developed to delineate Cost Account packages which are identified
and maintained in a responsibility assignment matrix.
12.6 Cost Schedule Performance Reporting (Optional Clause)
12.6.1 The Contractor submits to the Project Authority a monthly Cost Performance
Report (CPR), in CPR Formats 1, 2, 3, 4 and 5 in accordance with the United
States Department of Defense.
12.6.2 CPR Format 1 displays data for elements of the CWBS:
Level 1: All
Level 2: All
Level 3: WBS
WBS
etc....
12.6.3 The threshold for variance reports in CPR Format 5 is determined by
percentage and/or currency variation and varies with the Contract progress as
follows:
Project% %Margin and/or $Threshold Complete (+/-) 0-25% 26-75% 76-100%
12.6.4 The Contractor submits the report to the Project Authority within 14
days of the expiry of each month. The report may reflect data at the end of
the month or other accounting period used by the Contractor, but so as to be
consistent throughout the work under the Contract.
12.6.5 If the Project Authority notifies the Contractor on the basis of any
Cost Performance Report that it has failed to maintain satisfactory progress
in work under the Contract, the Contractor takes such measures as are necessary
to reestablish progress to the satisfaction of the Project Authority. The Contractor
advises the Project Authority of the measures taken and reflects the results
of such measures in subsequent reports.
12.6.6 Any reports submitted by the Contractor in relation to a Cost Schedule
Control System that is not validated contain a notation to that effect.
12.7 Subcontractor Cost Schedule Control Requirements (Optional Clause)
12.7.1 CSCSC Flowdown. If the subcontract requires work in excess of
12 months and the subcontract price exceeds $40m for development contracts and
$100m for all other contracts, the subcontractor maintains and uses in the performance
of the subcontract a Cost Schedule Control System in the same terms as required
of the Contractor under the Contract and as described in the Australian Cost
Schedule Control Systems Implementation Guide (ACSIG), DEF (AUST) 5657.
12.7.2 CSSR Flowdown. The Contractor shall require subcontracts who
are likely to be engaged in work in excess of 12 months and the subcontract
price exceeds $20m, but is less than $40m for development contracts and $100m
for all other subcontracts to operate a Cost Schedule Status Reporting system
in accordance the Cost Schedule Status Report Specification and Implementation
Guide DEF(AUST)5658.
12.7.3 The Project Authority may require, as a condition to the approval of
any subcontract, that the subcontract contains provisions requiring the subcontractor
to furnish to the Contractor Cost Performance Reports as follows:
a. if the subcontract requires work in excess of 12 months and subcontract
price exceeds $40m for development contracts and $100m for all other contracts,
the subcontractor provides a Cost Performance Report in CPR Formats 1, 2, 3,
4, and 5;
b. if the subcontract requires work in excess of 12 months with a subcontract
price of more than $20m but less than $40m for a development contract and less
than $100m for all other contracts, the subcontractor provides a Cost Performance
Report in CPR Formats 1, 3 and 5; and
c. if the subcontract contains critical tasks agreed between the Contractor
and the Project Authority, the subcontractor provides Cost Performance Reports
in CPR Formats 1, 3 and 5.
12.7.4 The Contractor incorporates data from subcontractor's cost performance
reports required by the Contract in its own cost performance reports to the
Project Authority, and upon request, provides the Project Authority with a copy
of the subcontractor's reports.
12.7.5 The Contractor establishes procedures which furnish for all subcontractors
others than those which are required to provide cost performance reports:
a. adequate indicators of subcontractors performance; and
b. identification, cause and impact of subcontractor schedule or technical problems.