Project description

This project is acquiring a Heavyweight Torpedo (HWT) for the six Collins Class submarine to replace the United States Navy’s (USN) Mk 48 Mod 4 HWT previously in service with the Royal Australian Navy (RAN). The torpedo is being supplied by the United States (US) Government under a Memorandum of Understanding (MOU), with work performed by Raytheon US and the US Naval Undersea Warfare Center.

The project is also acquiring associated logistic support, weapon system interface equipment, and operational support and test equipment. ASC Pty Ltd is undertaking integration to the Collins Class submarine platform.

Deliverable Original Planned Achieved / Forecast Notes

Project Year of Commencement

Jul 2001

Initial Materiel Release (IMR)

N/A

Mar 2008

 

Initial Operational Capability (IOC)

Feb 2008

May 2008

Variance is attributable to the Navy Regulatory Review process.

Final Materiel Release (FMR)

Nov 2013

Aug 2018

FMR date was set before the FCD program had reached maturity in terms of the length of dockings and impact of emergent work and other capability upgrades. As a result, the HWT installation schedule has been delayed.

Final Operational Capability (FOC)

Nov 2013

Sep 2018

Achievement of FOC is dependent on Navy. The capability delivered by the project is consistent with the MAA and FOC will be achieved when the Capability Manager confirms all other Fundamental Inputs to Capability are complete.