Volume 2, Chapter
1
2
3
4
5
6
7
Appendices
Index & Glossary
Download
Chapter 2

Outcome Performance

An overview of the DMO's performance against its outcome and outputs including Top 30 projects by 2005–06 expenditure and projects and products of emerging interest.

Output 1.1: Management of Capability Acquisition

Acquisition Projects not Included in the Top 30—Current Status

Table 2.6 provides an update on the status of projects included in statutory reports over the previous three financial years. The planned expenditure for these projects during 2005–06 places them outside of the Top 30.

Table 2.5 Projects and Products of Emerging Interest 2005–06
Title Project Number Project Description Approved Project Expenditure $m(1) Cumulative Expenditure to 30 June 2006 $m 2005–06
Expenditure
$m
Status Report
Air Warfare Destroyer SEA 4000 Ph2 An affordable maritime air warfare capability to the ADF. This will be a complementary part of the layered air defence capability. 460 51 51 First pass approval was achieved in May 2005, concurrent with the announcement of ASC Pty Ltd as the preferred shipbuilder. Raytheon Australia and Gibbs & Cox have been selected as the preferred Combat System-Systems Engineer and 'Evolved' Platform System Designer respectively. The Gibbs & Cox 'Evolved' design will compete with an Australianised version of Navantia's 'Existing' design F100 Destroyer. The Project is on schedule to present a fully developed comparison of the cost, schedule and capability of the two design options for Government consideration as part of second-pass approval planned for July 2007.
Amphibious Watercraft Project JP 2048 Ph1A Six amphibious watercraft for delivery to the Army. The platform will be capable of deployment with the Landing Platform Amphibious ships. 58 36 23 All watercraft have achieved initial operational release and are operating in service, with project management responsibility transferred to the Amphibious and Afloat Support Program Management Office. In accordance with the project closure plan, the last items in project closure arrangements are being finalised.
Amphibious Assault Ship (LHD) Project JP 2048 Ph4A/4B An increased amphibious deployment and sustainment capability to support an enhanced deployed force. 38 17 11 Not yet to contract. Assessment of two suitable existing ship designs continues. Government first-pass approval was achieved in August 2005, releasing approximately $30m for first and second pass activities. Australian industry was briefed on first-pass outcomes. Design development activity with resident project teams in France and Spain was completed on 3 April 2006. The Request for Tender for design and construction of the LHDs was released, on schedule, on 28 April 2006. The Defence Capability Plan 2006–16 budget for this project is $1.5 to $2 billion.

Note:

  1. 2005–06 Additional Estimates indexation and foreign exchange parameters.
Table 2.6 Update of Status of Previously Reported Top 30 Projects (Financial Years 2004–05, 2003–04 and 2002–03)
Title Project Number Approved Project Expenditure $m(1) Cumulative Expenditure to 30 June 2006 $m 2005–06
Expenditure
$m
Status Report
Aerospace
F/A-18 Hornet Structural Refurbishment Program—Stage 1 AIR 5376 Ph3.1 121 75 18 Following successful prototype of the modification on an aircraft in January 2004, the project is now into the production phase with 23 aircraft delivered to July 2006. Production is expected to continue through to December 2008 at RAAF Williamtown.Costs are forecast to exceed the programmed outlays for 2005–06 due to the additional cost of unexpected damage found during aircraft teardown in the Hornet Upgrade Phase 3.1 modifications.
Lead-in Fighter Capability AIR 5367 Ph1 1,023 1,000 37 This project involves the acquisition of 33 Hawk A27 aircraft to perform lead-in fighter and ADF support roles. Aircraft delivery was completed in October 2001. The final operational capability for radar simulation function has been delayed due to technical difficulties. This capability is currently under test and evaluation to facilitate final acceptance. The project underachieved against estimates due to these delays.
Maritime
Mine Hunter Coastal Acquisition SEA 1555 Ph2 1,246 1,143 10 All vessels have been accepted into service. The underspend in 2005–06 was due primarily to the prime contractor's limited resources being focused on delivering in-service support activities, including the deactivation and short-notice reactivation of two vessels, as opposed to finalisation of outstanding acquisition contract changes.
Evolved SeaSparrow Missile SEA 1428 Ph2ASEA 1428 Ph2B/3 354274 348243 -21 Progressive missile deliveries, which included the last of the Phase 2A missiles, occurred throughout 2005 and will continue in 2006–07 and subsequent years. All Anzac-class frigates have been fitted with the Evolved Seasparrow missile system with the last ship, HMAS Anzac, upgraded in June 2006 during that ship's recent major maintenance period.
Collins Class Submarine Augmentation SEA 1446 Ph1 233 204 4 All major elements are complete. The remaining activity under this project is the platform training simulator upgrade, the procurement strategy for which is almost complete. Placement of a contract is anticipated later in 2006. Expenditure for the year was slightly more than the revised estimate due to the ability to purchase spares items earlier than planned.
New Submarine Project SEA 1114 Ph3 5,121 5,072 5 The last of the six submarines was delivered in March 2003. A number of minor activities were progressed in preparation for project closure. Expenditure for the year was slightly more than the revised estimate due to ASC Pty Ltd's ability to take on additional minor tasks.
Land
Direct Fire Guided Weapon LAND 40 145 92 32 Delivery of the Javelin Command Launch Units and Outdoor Training Systems was completed in April 2006. The training systems were delivered 12 months ahead of the original contracted schedule. Javelin has been deployed operationally with trained personnel and logistical support in Iraq and Afghanistan.
Ground Surveillance Radar LAND 53 Ph1 84 86 22 The key outcomes expected in 2005–06 were the delivery of the remaining production equipment, commencement of the through-life support contract, and completion of the service training activities. These outcomes were achieved on schedule. Completion of the acquisition contract was achieved earlier than forecast in June 2006.
Electronic and Weapon Systems
Air-to-Surface Stand-Off Weapon Capability AIR 5398 Ph1 441 383 21 AIR 5398 successfully completed the initial operational test and evaluation program including two live missile firings at the Woomera Test Range in October 2005. Chief of Air Force subsequently granted service release for the employment of the AGM-142E weapon on the F-111C aircraft fleet in May 2006, and initial operational capability was declared in June 2006.
Air-to-Air Weapons Capability AIR 5400 Ph1 313 277 11 Both missiles have been released into service with the Air Force and the project is transitioning the full capability to the in-service management agencies. The final item to transition is the maintenance and software support facilities contract for the advanced short-range air-to-air missile, which will be transferred to in-service management late in 2006.
Tactical Air Defence Radar Systems AIR 5375 Ph1 207 165 13 The Australian Government took acceptance of Tactical Air Defence Radar System from Lockheed Martin Corporation in November 2005. Financial withholds were put in place pending the close-out of defects and omissions noted at acceptance.The Tactical Air Defence Radar System is now in operational use with the Air Force. A long-term installation operating permit for the new radar system was issued by Commander Surveillance and Response Group on 12 July 2006. In-service support arrangements, including contractor support, are in place. Project office closure and project transition was concluded in July 2006.
E-Defence ProjectTransferred to Chief Information Officer Group JP 2054 Ph1 116 54 1 E-Defence aims to provide the infrastructure for a corporate electronic identity framework. The project will develop infrastructure to enhance current e-mail systems with a corporate directory service.All major procurement activity is paused pending both a re-assessment of requirements and revision of the acquisition strategy; completion of both documents is scheduled for May 2007. Delays in completing the re-assessment of requirements and revision of the acquisition strategy have arisen due to the longer than planned requirements development phase and industry's evolving ability to deliver a commercial-off-the-shelf solution. Responsibility for the acquisition and implementation of the capability was transferred to the Chief Information Officer Group from the DMO.

Note:

  1. 2005-06 Additional Estimates indexation and foreign exchange parameters.

Back to top