Approved Major Capital Equipment Projects
In the DMO's role of supporting Defence capabilities through efficient and effective acquisition and sustainment of equipment for the ADF, DMO manages the approved major capital investment program.
The approved major capital equipment program consists of projects costing generally in excess of $20m and which, following approval, are transferred from the Defence Capability Plan to the DMO for their acquisition phase. Projects costing less than $20m are generally categorised as minor capital projects and are part of the other capital purchases category, although individual project phases within the Defence Capability Plan, such as studies, can cost less than $20m.
Table 6.1 and accompanying descriptions provide details of the approved project cost, cumulative expenditure to 30 June 2005 and actual expenditure for 2004-05, of the top 30 (by 2004-05 expenditure) major capital equipment projects.
Table 6.1 Top 30 Projects by Actual 2004-05 Expenditure(1)
| Project |
Project
Number |
Approved
Project
Expenditure
(2) |
Cumulative
Expenditure
(3) |
2004-05
Budget
Estimate
(4) |
2004-05
Revised
Estimate
(5) |
2004-05
Actual |
| |
|
$m |
$m |
$m |
$m |
$m |
| Aerospace |
| Airborne Early Warning and Control |
AIR 5077 Ph 3 |
3,455 |
2,071 |
462 |
497 |
518 |
| Armed Reconnaissance Helicopter |
AIR 87 Ph 2 |
1,964 |
806 |
445 |
419 |
382 |
| ADF Air Refuelling Capability |
AIR 5402 |
1,833 |
189 |
214 |
208 |
188 |
| F/A-18 Hornet Upgrade |
AIR 5376 Ph 2 |
1,474 |
789 |
134 |
155 |
175 |
| P-3C Update Implementation |
AIR 5276 |
905 |
836 |
48 |
45 |
43 |
| Anzac Ship Helicopter |
SEA 1411 Ph 1 |
1,001 |
918 |
60 |
29 |
29 |
| F/A-18 Hornet Structural Refurbishment Program - Stage 1 |
AIR 5376
Ph 3.1 |
120 |
57 |
23 |
27 |
26 |
| Maritime |
| Anzac Ship Project(6) |
SEA 1348 |
5,368 |
5,052 |
220 |
190 |
170 |
| Collins Replacement Combat System |
SEA 1439
Ph 4A |
443 |
208 |
158 |
138 |
127 |
| Armidale-class Patrol Boat |
SEA 1444 |
477 |
100 |
81 |
78 |
77 |
| New Heavyweight Torpedo |
SEA 1429 Ph 2 |
414 |
131 |
31 |
44 |
59 |
| FFG Upgrade Implementation |
SEA 1390 Ph 2 |
1,464 |
965 |
137 |
71 |
54 |
| Evolved SeaSparrow Missile |
SEA 1428
Ph 2B/3 |
273 |
222 |
43 |
48 |
47 |
| Collins-class Reliability and Sustainability Improvements |
SEA 1439 Ph 3 |
371 |
146 |
55 |
36 |
31 |
| Anti-Ship Missile Defence |
SEA 1448
Ph 2A |
496 |
9 |
31 |
20 |
8 |
| Land |
| Australian Light Armoured Vehicles |
LAND 112
Ph 3 |
672 |
522 |
58 |
57 |
50 |
| Upgrade of M113 Armoured Vehicles |
LAND 106 |
589 |
182 |
34 |
46 |
44 |
| Direct Fire Guided Weapon |
LAND 40 |
142 |
60 |
35 |
33 |
36 |
| Ground Surveillance Radar |
LAND 53
Ph 1E |
84 |
64 |
27 |
7 |
19 |
| Bushranger Infantry Mobility Vehicles |
LAND 116 |
352 |
116 |
32 |
26 |
15 |
| Electronic and Weapon Systems |
| Jindalee Operational Radar Network |
JP 2025 Ph 3/4 |
1,244 |
1,137 |
36 |
36 |
42 |
| Milsatcom - Ground Infrastructure |
JP 2008 Ph 3E |
148 |
73 |
52 |
45 |
38 |
| Air-to-Surface Stand-Off Weapon Capability |
AIR 5398 |
440 |
362 |
28 |
30 |
33 |
| High Frequency Modernisation |
JP 2043 |
608 |
306 |
30 |
31 |
31 |
| Air-to-Air Weapons Capability |
AIR 5400
Ph 1/2 |
313 |
266 |
31 |
30 |
31 |
| Lightweight Torpedo Replacement |
JP 2070 Ph 2 |
319 |
113 |
75 |
44 |
29 |
| Electronic Warfare Self-Protection for Selected ADF Aircraft |
AIR 5416 |
290 |
29 |
28 |
20 |
27 |
| New Air Defence Command and Control Systems for 2CRU/3CRU(7) |
AIR 5333 |
248 |
68 |
38 |
21(8) |
24 |
| Air-to-Air Weapons Follow-on Buy |
AIR 5400 Ph 3 |
175 |
132 |
23 |
10 |
15 |
| New Air Combat Capability |
| New Air Combat Capability |
AIR 6000 SDD |
211 |
92 |
53 |
27 |
26 |
| Total Top 30 Projects |
25,893 |
16,021 |
2,722 |
2,468 |
2,394 |
Notes
- Variations in approved project expenditure since the publication of the Portfolio Additional Estimates Statements 2004-05 are a result of price indexation and exchange rate adjustments excluding AIR 5077 Phase 3 Airborne Early Warning and Control aircraft (which transferred $1m to Corporate Services and Infrastructure Group for facilities work) and AIR 5376 Phase 2 F/A-18 Hornet Upgrade (which reduced approval by $67m following the Government's decision to revise scope for the project).
- 2005-06 Budget prices.
- Expenditure to 30 June 2005.
- 2004-05 Budget prices.
- 2004-05 Additional Estimates prices.
- Project approval, expenditure and estimate figures are the net cost of the ten-ship program after deducting New Zealand payment.
- Project title previously reported as '2CRU/3CRU Control and Reporting Units'.
- The revised estimate for AIR 5333 included in the Portfolio Additional Estimates Statements 2004-05 was incorrectly reported as $30m. The correct value should have read $21m.
|