Chapter Two - Capital Budget > Capital Facilities Projects > page 11 of 16
| |

Capital Facilities Projects

Approved Medium Capital Facilities Projects

Table 2.5
continued
Approved Medium Capital Facilities by State and Federal Electorate (1)
Program of Medium Works
(State, Federal Electorate and Locality)
Total
Estimated
Expenditure
$'000
Cumulative Expenditure (2)

$'000
2004-05
Budget
Estimate
$'000
2004-05
Revised
Estimate
$'000
2004-05
Actual

$'000
Queensland
Brisbane
Enoggera
Bushmaster Critical Infrastructure Upgrade (formerly critical infrastructure upgrade) 3,200 340 3,160 3,000 340
Australian Light Armoured Vehicle Workshops 4,500 3,179 2,250 2,250 3,179
Groom
Oakey - Museum of Army Flying 1,935 (3) 1,065 - 1,000 1,065
Herbert
Townsville
Lavarack Barracks - Helicopter Underwater Escape Training Facility 2,235 (9) 129 2,400 500 114
Lavarack Barracks - Regional Training Centre (Flexible Learning) 3,995 (3) 3,995 3,500 3,500 3,834
Combat Training Centre (Live) Storage and Maintenance Facility 2,800 761 (4) 2,500 1,800 745
Special Operations Forward Mounting Facility (5) 1,400 665 1,400 1,400 665
Lavarack Barracks Frontline Redevelopment of Mess 341 341 - 341 341
RAAF Townsville - Base Training and Support Facility (7) 5,300 51 - - 51
Field Training Area Air Weapons Range (7) 4,200 47 - - 47
Mount Stuart
Training Area Grenade Range (5) 400 370 350 400 370
Total Queensland 30,306 10,943 15,560 14,191 10,751

Notes

  1. Addition of individual projects may not match State and column totals due to rounding.
  2. Cumulative expenditure to 30 June 2005.
  3. Increase in outturn cost.
  4. Incorrect values for the cumulative expenditure to 30 June 2004 were reported in the Defence Annual Report 2003-04 and the Portfolio Additional Estimates Statements 2004-05. See corrections to the Defence Annual Report 2003-04 on pp vi-vii.
  5. Regional delivery.
  6. Project completed. Budget decreased, omitted from Defence Annual Report 2003-04.
  7. Project approved by departmental delegate after the publication of the Portfolio Additional Estimates Statements 2004-05.
  8. Approved by the Minister for Defence after the publication of the Portfolio Additional Estimates Statements 2004-05.
  9. Decrease in outturn costs.
  10. Project deferred.
  11. Project approval awaiting environmental clearances.
| | « Previous | Home | Next » |