Capital Facilities
Major Works
The following summaries only refer to those projects that have had significant expenditure in 2002-03.
Eden, New South Wales - Naval Ammunitioning Facility
Partially Achieved
This project provides a naval ammunitioning facility to replace the former facility at Newington on the Sydney Olympics site. The project objectives for 2002-03 were to continue construction of the wharf and commence construction of the ammunition storage depot. Construction of the wharf commenced in March 2002 and is scheduled to be completed in September 2003. Work commenced on the ammunition storage facilities in February 2003 and is scheduled for completion in late October 2003. While expenditure during the year was significantly less than the revised forecast, which was based on an unachieved accelerated program, the facility remains on track for completion this year.
Nowra, New South Wales - HMAS Albatross Base Redevelopment
Partially Achieved
This two-stage project aims to replace existing facilities and services that are beyond economical repair and to redevelop the operational and administration support facilities. The project objectives for 2002-03 were to largely complete the two outstanding works items - the engineering services and the flight deck procedural training facilities. Engineering services were delayed due to issues associated with refining the scope of work. Construction of the flight deck procedural trainers has been delayed due to siting issues.
Ermington, New South Wales - Pre-Disposal Site Works
Partially Achieved
The aim of these works is to prepare the 20-hectare site on the Parramatta River for disposal. The work involves progressive site filling and stabilisation and the installation of trunk infrastructure to enable the site to be sold progressively as a series of 'super lots'. Development approval was expected in December 2002 but is now not expected until November 2003.
Williamtown, New South Wales - RAAF Williamtown Redevelopment Stage 1 and Airborne Early Warning and Control Works
Partially Achieved
This project will provide a range of new and redeveloped facilities and infrastructure necessary for the introduction into service of the airborne early warning and control capability to be based at RAAF Williamtown. The project was approved by Parliament in September 2002. Construction of 2 Squadron Headquarters commenced in May 2003 as a separate head contract to permit completion by January 2004. Appointment of the managing contractor for delivery of the balance of the work has been delayed due to the introduction of new Defence processes and revised contracts, but project completion remains on schedule for the end of 2006.
Fishermans Bend, Victoria - Relocation of Defence Science and Technology Organisation's Platforms Sciences Laboratory
Partially Achieved
This project will relocate science and technology functions from Maribyrnong to Fisherman's Bend. The project includes the integration of common functions and the construction of enhanced research and laboratory facilities and will permit the subsequent disposal of the Maribyrnong site. Cost overruns necessitated reduction in the project scope and the majority of the reduced scope was expected to be delivered in 2002-03. Wet weather, some industrial action and contractor delays associated with tendering in an overheated construction market resulted in the program falling short of forecast.
Canungra, Queensland - Defence Intelligence Training Centre
Substantially Achieved
This project will provide new working accommodation for the headquarters, administration, instruction and course development elements. The majority of the works, less fit out, were planned to be completed in 2002-03. Wet weather caused significant delays to the program but recent progress has been good. The project is due for completion in late 2003.
Oakey, Queensland - Oakey Base Redevelopment
Achieved
This project will redevelop the base for optimal support of Army rotary wing flying training. The revised program was achieved and construction should be completed by mid-2004.
Townsville, Queensland - Lavarack Barracks Redevelopment Stage 3
Achieved
This project provides new working facilities for Army units at the barracks. New facilities for 2nd Battalion the Royal Australian Regiment are now complete. Similar new facilities for 1st Battalion the Royal Australian Regiment commenced construction in January 2003 and will be completed by November 2004. Good progress has been achieved on the project resulting in a slight acceleration of the program.
Townsville, Queensland - RAAF Townsville Redevelopment Stage 1
Achieved
This project provided new facilities, including ordnance loading aprons and aircraft and vehicle support infrastructure. Major elements of the project were programmed for completion by August 2002 and this was achieved.
Townsville, Queensland - RAAF Townsville Redevelopment Stage 2
Achieved
This project provides a range of new facilities to contemporary standards to replace existing facilities. Transit accommodation was completed in July 2003. Other major new facilities currently under construction include the main base entrance and physical fitness, air movements and combined messing facilities. Progress on the project has been good and all of these works will be completed by February 2004.
Edinburgh, South Australia - RAAF Edinburgh Redevelopment Stage 1
Achieved
This project will provide new administrative, workshop and warehousing facilities and an aircraft shelter, as well as an upgrade of engineering services. Construction has progressed well with most facilities completed. The warehousing facility is scheduled for completion in October 2003.
Darwin, Northern Territory - RAAF Darwin Base Redevelopment Stage 1
Partially Achieved
This project provides enhanced support facilities at RAAF Darwin. The majority of the facilities have been completed and are in use. The program was not achieved during 2002-03 due to delays in finalising the scope of the base medical facilities and firefighting water supply. These are now in the design stage and will be completed by mid-2004.
Timber Creek, Northern Territory - Bradshaw Field Training Area Infrastructure
Partially Achieved
This project will provide engineering services and infrastructure to allow the use of Bradshaw as a field training area for 1 Brigade. Initial works to construct a bridge over the Victoria River allowing access to the Bradshaw property were completed in October 2002. Estimated expenditure was not achieved due to delays in negotiating the indigenous land use agreement. With the signing of the agreement in July 2003, contracts for civil works, including road and airfield construction, will be let by the end of 2003 subject to registration of the agreement. Construction is now expected to commence in early 2004 and be completed by the end of 2005.
Canberra, Australian Capital Territory - Defence Network Operations Centre
Achieved
This project provides facilities at HMAS Harman to allow for installation of a range of communications activities. Due to good contractor performance, the program was accelerated slightly. The forecast achievements were met, with completion of the facility in July 2003.