Simulation and CD&E

ADSO have developed a simulation support process to assist desk and procurement officers in the development, acquisition and support of Major and Minor Capability Equipment. The process is detailed in the following pages of the Capability Development Process Map. Feedback to improve the process is most welcome.

First Pass

Form First Pass and Perform Initial IPT Planning Activities (CDG 2.2.1.1)
Develop Draft PMP to Achieve First Pass (CDG 2.2.1.1.1)
Form First Pass IPT (CDG 2.2.1.1.2)
Develop Supporting Plans to Achieve First Pass (CDG 2.2.1.1.5)
Develop/Endorse Project & ISS Budget (First Pass) (CDG 2.2.1.3.4)
Perform/Approve Risk Assessment (First Pass) (CDG 2.2.1.3.6)
Develop Initial Business Case for Each Viable Option (CDG 2.2.1.4)
Prepare Initial Business Case Sections Using Capability Baseline Documents (CDG 2.2.1.4.1)
Comparative Analysis of Initial Business Cases (CDG 2.2.1.5.1)
Develop Proposal Body and Supporting Annexes (CDG 2.2.1.5.2)

Second Pass

Form Second Pass IPT & Perform Initial IPT Planning Activities (CDG 2.2.2.1)
Form Second Pass IPT (CDG 2.2.2.1.1)
Develop Supporting Plans To Achieve Second Pass (CDG 2.2.2.1.4)
Develop Final PMP To Achieve Second Pass (CDG 2.2.2.1.5)
Baseline Product Development For Each Option (Second Pass) (CDG 2.2.2.2)
Develop/Endorse Project & ISS Budget (Second Pass) (CDG.2.2.2.2.4)
Perform/Approve Project Risk Assessment (Second Pass) (CDG.2.2.2.2.6)
Develop Acquisition Business Case For Each Option (CDG 2.2.2.4)
Develop Acquisition Business Case Sections Using Capability Baseline Documents (CDG 2.2.2.4.1)
Develop Draft Plans to Achieve Acquisition Phase For Option (CDG 2.2.2.4.2)
Comparative Analysis of Acquisition Business Cases (CDG 2.2.2.5.1)
Develop CP 2nd Pass Body and Supporting Annexes (CDG 2.2.2.5.2)

Combined Pass

Review Capability Requirement (CP 1.1)
Re-Establish IPT and Perform IPT Activities (CP 1.1.2)
Update Capability Baseline Documents (CP 1.1.3)
Update and Endorse Project and ISS Budget (Second Pass) (CP 1.1.3.4)
Update and Approve Project Risk Management Plan (Second Pass) (CP 1.1.3.6)
Source Other Stakeholder Enabling Products (CP 1.1.3.8)
Develop Acquisition Business Case (CP 1.3 )
Develop Draft Plan to Achieve Updated Acquisition Phase (CP 1.3.2)
Develop Capability Proposal Second Pass (CP 1.4)
Conduct Comparative Analysis of Acquisition Business Cases (CP 1.4.1)
Develop CPSP Body and Supporting Annexes (CP 1.4.2)
Undertake Stakeholder Review and Endorsement of CPSP (CP 1.4.3)